Pequannock Township

Town-wide Park and Recreation Master Plan

 

Morris County, New Jersey

 

Prepared by:

Professional Planning and Engineering, a division of Pennoni Associates, Inc.

September 2007

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

i

 

Acknowledgements

 

The development of this Town-wide Park and Recreation Master Plan was a

cooperative effort between the Township administration, staff and volunteers, local

recreation groups and individuals. We thank all of the people and organizations listed

below for their input, guidance & direction in the formulation of this master plan

document.

 

Joel D. Vanderhoff

 

Mayor

 

Kevin P. Boyle

 

Township Manager

 

Pequannock Township Council

 

Joel D. Vanderhoff, Mayor

Ed Englebart

Joseph L. Jorgensen

Nicholas Kapotes, Parks and Recreation Advisory Board Liaison

Louis A. Skvarca

 

Pequannock Township Parks and Recreation Department

 

Denise Furfaro, Director

Renee Helmer, Program Coordinator

 

Pequannock Township Parks and Recreation Advisory Board

 

Jan Vanderhoff, Chairperson

William Zickler, Vice Chairperson

Robert Jones

Maureen McMahon

Dawn Skvarca

David Swezey

Douglas Troast

Bruce Vitcavich

Past Member: Evelyn Roosma

 

Pequannock Township Recreation Organizations

 

Boys and Girls Club of Northwest New Jersey

Pequannock Lacrosse Club

Pequannock Little League

Pequannock Soccer Club

 

Acknowledgements

PENNONI ASSOCIATES INC.

Consulting Engineers

 

ii

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Executive Summary

 

Figure 1 ~ Pequannock Township location in Morris

County showing related open waters.

 

Pequannock Township’s unique location

at the confluence of three rivers and at

the base of mountains and the

Township’s history affords the

Township the opportunity to provide its

residents with a wide variety of

recreation and leisure opportunities.

Pequannock Township has 646.6 acres

of open space land utilized for park

and recreation purposes. Twenty four

acres (24-acres) of two parks,

Rockledge and Cherry Street parks,

remain undeveloped. The developed

parks provide a variety of recreational

opportunities ranging from hiking,

playgrounds, athletic fields and courts,

picnic areas, lake swimming, boating,

fishing and camping.

This Town-wide Park and Recreation Master Plan (Master Plan) evaluates the number

and quality of facilities provided to Pequannock Township residents against the

anticipated needs and provides recommendations for improvements and acquisitions to

meet the anticipated demand for recreational facilities in the Township.

 

VISION, MISSION AND GOALS

 

The Township’s Recreation Advisory Board and Park and Recreation Director developed

vision and mission statements and goals and objectives to set the framework for the

master plan. See Chapter 2 to review the objectives and associated statements.

 

Vision

 

To provide a well rounded recreation and leisure experiences for all members of the

community.

 

Mission Statement

 

The Township will meet the physical, mental, cultural and social needs of Pequannock

residents by providing the best possible overall park system through programs,

services, facilities and structures and by preserving and developing new and existing

lands and their improvements.

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

iii

 

Acknowledgements

PENNONI ASSOCIATES INC.

Consulting Engineers

 

iv

 

Goals

 

Goal 1: To improve the quality of life for community residents.

Goal 2: Ensure equitable access to safe and attractive parks and facilities that meet

community needs.

Goal 3: Actively pursue adequate open space for future recreation facilities.

Goal 4: To preserve and enhance the social and ecological environment for Township

residents.

Goal 5: Implement and update the Parks and Recreation Master Plan (PRMP) so it

remains a dynamic guide for the Park and Recreation Department.

Goal 6: Management of the park system to the highest standards.

 

DEMOGRAPHIC ANALYSIS

 

We must remember as we go through the planning process for the Township-wide

Recreation Master Plan that we are planning for people. Since the level and quantity

of parks and recreation services demand is directly related to the number of people

demanding the given services, changes in both the number and composition of that

local population affects local government planning. A youthful population makes

different demands on parks facilities than a much older population does, and an

increase in certain cultural groups – Hispanics, for example- can create yet another set

of demands.

Since estimates of population change are crucial to planning, budgeting and financing

park improvements, they are essential to this Master Plan.

The population has been increasing in Pequannock over the last decade and, according

to the most recent Census information, is predicted to continue to rise. The greatest

change over the last decade is found in the under 5 age group and 65 and older age

group with an increase of 21.72% and 25.38% respectively. The remaining age groups

are remaining stable or increasing slightly over the last decade at 0.52% for age 5-24,

5.08% for age 25-44 and 9.55% for age 45-64.

The largest percent of the population at 29.64%, however, is found in the 25-44 age

group. Township residents age 5-24 have been steadily decreasing over the last thirty

years and they do not dominate the Township population now as they had done

historically. Age 5-24 and age 45-64 make up a similar ratio of the population at

24.83% and 24.63% respectively. Residents 65 and older make up 14.08% of the

population and children under 5 make up 6.82% of the population.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

v

 

RECREATION STANDARDS AND NEEDS ASSESSMENT

 

Balanced Land Use Guidelines

 

New Jersey’s State Comprehensive Outdoor and Recreation Plan identifies the goal for

New Jersey municipalities to provide three percent (3%) of the total developable lands

within the municipality for recreation uses. This balanced land use approach takes

into consideration the extent of wetlands and steep slopes in the municipality and

removes those lands from the total developable lands within the municipality.

According to this methodology Pequannock Township, with its 647 acres of park land,

has preserved fourteen percent (14%) of its overall lands and thirty percent (30%) of

the Township’s developable lands for recreation purposes.

This analysis is unevenly balanced, however, due to eighty-two percent (82%) of the

preserved lands suitable only for passive recreation or resource areas due to wetlands

and steep slopes on the site. So while there is a significant amount of lands preserved

for recreation purposes the Township does not have a balance between lands suitable

for active and passive recreation.

 

Population-based Recreation Open Space Needs Assessment

 

In 1995, the National Recreation and Park Association (NRPA), in collaboration with

the American Academy for Park and Recreation Administration, published “Park,

recreation, Open Space and Greenway Guidelines.” The revised guidelines

acknowledge that each community is unique, and that it is difficult to apply one set of

special standards to all communities as had been done in the past. Instead, the

guidelines reflect a more systematic planning approach that takes into account the

unique needs, desires and resources of communities as well as changing

environmental, social, economic and demographic trends.

With this framework in mind, the NRPA takes a different approach to park planning,

analyzing the types of parks and facilities required for each individual community,

along with the amount of acreage required to site those kinds of parks and facilities.

The process includes identifying the classifications of parks and the level of service for

each facility within each park classification.

Table 1 below identifies Pequannock Township’s parks by classification, the

recommended acreage per classification and the surplus or deficit per classification.

There are no recommended standards for special use parks or natural resource areas.

Review of the table shows that based upon this analysis there is a deficit of park land

in all classifications with the greatest deficit in the Sports complex classification.

 

Acknowledgements

 

Table 1 ~ Parks by classification, standards and deficiencies / surplus

 

Recreation Need by Park Classification

 

The majority of the Township parks are located in the central to southern area of the

Township. This is most likely due to the location of wetlands and floodplain

influencing the initial settlement of the Township with the first homesteads in the

north central section of town. When parks and recreation development came to the

forefront there was more opportunity to set aside lands for recreation and leisure in

the central and southern part of town. This provides an imbalance to access to the

provided parks and their recreation and leisure facilities. The residents in the

southern and south-central part of the Township have better access to facilities than

those in the north and north-central part of the Township.

When evaluating the deficit of park classifications and the typical uses within those

park classes the park classification hierarchy is taken into consideration. For example,

the facilities found in a Mini Park may also be found in all of the other park

classifications except Natural Resource Area and Greenways. This could mean that a

Neighborhood Park can supply the demand for a Mini Park depending upon the location

within the Township.

In addition, School Complexes may also partially supply the demand for certain park

classifications based upon the available facilities and availability for use. In

Pequannock, Stephen J. Grace and Hillview Elementary Schools have playgrounds.

 

PENNONI ASSOCIATES INC.

Consulting Engineers

 

vi

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

vii

They may act as Mini Parks, Neighborhood Parks or Sports Complexes during non-school

hours.

 

Mini Parks

 

Mini Parks and the typical facilities of such parks are well distributed in the southern

section of town. In addition to Lyon Park and Riverside Park, Greenview Park and

Stephen J. Grace Elementary School are in the southern section of town. These

provide the facilities that a Mini Park would and are well distributed in the southern

section of town.

Hillview Elementary School serves as a Mini Park in the center of town. There is a gap

in service for the residents to the south and west of the school.

Two sites in the northern section of the Township provide the facilities found in a Mini

park, North Boulevard School and Foothills Park. Both sites have a playground.

Access to Foothills Park, however, is by vehicle not by foot as there is no safe

pedestrian access to the park. There is a gap in service between Hillview and North

Boulevard Schools north and south and east to west in the Township.

 

Neighborhood Parks

 

The Neighborhood Parks are located at opposite ends of the Township (northwest and

southeast). Greenview Park, a Community Park, can serve the need as a Neighborhood

Park. There is a gap in service with no Neighborhood Park in the central or the

northeast section of town.

 

Community Park

 

Greenview Park is the only Community Park within the Township. This serves the

residents in the southwest corner of town with a gap in service for the remainder of

the Township.

 

Sports Complex

 

Sports Complex should be strategically located within the Township. The current

facilities are centrally located on the eastern side of town.

 

School Complex

 

The schools in Pequannock Township are located in the north-south central corridor.

They serve as Mini Parks, Neighborhood Parks, and Sports Complexes. As these lands

are not managed by Pequannock Township they were not included within the

surplus/deficit calculations but will be considered as part of the facility

recommendations.

 

FACILITY NEED

 

This Master Plan evaluates the facility demand based upon previous information

discussed in this report, input from the Parks and Recreation Director, the Recreation

 

Acknowledgements

PENNONI ASSOCIATES INC.

Consulting Engineers

 

viii

Advisory Board and stakeholders. This information as well as analyzing the

geographical location of the facilities was used in developing the facility needs.

Pequannock Township provides a variety of indoor and outdoor recreation and leisure

opportunities for residents. There is a need for additional facilities to support the

demand for these programs.

The outdoor facilities provided include boating, camping, fishing, hiking and nature

trails, picnic areas, ice skating, playgrounds, swimming and athletic fields. The

Township also has a Senior Center. The Township has a need to provide 3-4 additional

soccer/lacrosse fields and one baseball field to meet the growing demand. The other

outdoor activities are adequate in number. There are opportunities to capitalize on

the undeveloped lands to augment these facilities. This, however, is not a priority.

The Township does not have any facilities to support other indoor programs such as

basketball, volleyball, jazzercise, aerobics, little crafters, hands on fun, children’s

ceramics, karate, etc. The Parks and Recreation Department relies on Board of

Education (BOE) facilities for these programs. Time and space for these programs in

BOE facilities is getting less and less over the years as the BOE before school and after

school programming is expanding. The Township needs an indoor facility to continue

to be able to provide the level of programming and services the residents are

accustomed to and the Township has the ability to provide with available facilities.

 

RECOMMENDATIONS

 

The following are actions to be completed based upon recommendations discussed in

Chapter 7 of this report. The tasks are listed in priority order within each task category.

 

Immediate Actions (within one year)

 

1. Complete Greenview Park parking reconfiguration improvements.

2. Develop an action plan to pursue funding sources identified in the Open Space

and Recreation Plan to fund the recommended improvements.

3. Acquire funding to implement Hillview Fields improvements.

4. Remove DPW dump yard from Washington Park and remediate to residential

standards. Conduct a pre-application meeting with the NJ DEP to discuss the

proposed improvements.

5. Complete topographic and utility mapping for Washington Park improvements.

6. Develop and implement a comprehensive maintenance operations tasks and

schedule for each facility.

7. Begin negotiations for acquisition / agreement for use of Block 902 Lot 4 as a

soccer / lacrosse field with supporting parking.

8. Continue dialogue with the Board of Education on shared use for athletic fields

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

ix

 

and existing field reconfiguration to expand field usage. Work with the sports

groups in town to leverage funding and manpower.

9. Further explore the programming and location for an indoor community

recreation facility.

10. Complete master plan for Pequannock Valley Park.

11. Develop a plan to coordinate all recreational opportunities and organizations

within the Township with possible shared scheduling of facilities.

12. Complete site development / park and recreation design guidelines.

13. Develop signage system and hierarchy.

14. Contact owners of farm assessed lands to encourage their participation in the

farmland preservation program.

 

Intermediate Actions (within three years)

 

1. Jointly implement Board of Education athletic field improvements with the BOE

and local recreation groups.

2. Develop a self-guided tour map along the adopted greenway identifying

cultural, social, recreational and environmental points of interest.

3. Complete wetlands mapping for Rockledge Park, Cherry Street Park, Hidden

Cove and Lyman Park.

4. Update Aquatic Park Master Plan

5. Develop “Friends of the Park” program.

6. Develop and adopt a Township Greenway Network.

7. Complete Hillview Fields Improvements.

8. Complete Washington Park improvements.

9. Complete Rockledge Park improvements

10. Implement signage improvements.

 

Intermediate Actions (within five years)

 

1. Complete soccer / lacrosse field improvements at Aquatic Park.

2. Riverside Park expansion feasibility study.

3. Complete Aquatic Park Master Plan recommendations.

4. Complete Hidden Cove improvements.

5. Complete Cherry Street Park improvements.

6. Implement Aquatic Park Master Plan.

7. Acquisition of parcels adjacent to Lyman Park (Block 4112 Lots 1&16).

8. Complete fundraising for Community Recreation Center.

 

Acknowledgements

PENNONI ASSOCIATES INC.

Consulting Engineers

 

x

 

Long Term Actions (within 10 years)

 

1. Implement Community Recreation Center.

2. Complete Woodland Lake improvements.

3. Complete remainder of Greenview Park improvements.

4. Update Park and Recreation Master Plan including the completion of a

statistically accurate user survey.

 

Ongoing Actions

 

1. Continued park maintenance.

2. Continue comprehensive maintenance operations tasks and schedule for each

facility.

3. Continued signage maintenance.

4. Continued streetscape improvements maintenance.

5. Add all new land acquisitions to the Township ROSI.

6. Actively participate in regional environmental issues (i.e. the Pia Costa Tract

wetland mitigation bank) and recreation issues (i.e. the Pequannock River

Trail).

7. Monitor land acquisition opportunities for use as recreational facilities.

8. Monitor environmental regulations and possible weakening of regulations which

would increase land acquisition for environmental preservation up in priority.

9. Work with Morris County to implement regional trails within the Township

including along the railroad right-of-way.

10. Designate a Recreation Advisory Board member as liaison to each of the

environmental, historic, open space and street tree commissions.

11. Encourage stewardship of the parks and social ties through the “Friends of the

Park” program.

12. Seek continued input from the community regarding recreation programs and

facilities.

13. Implement the fund raising action plan.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

xi

 

Table of Contents

 

ACKNOWLEDGEMENTS.........................................................................................................................I

EXECUTIVE SUMMARY........................................................................................................................III

 

VISION, MISSION AND GOALS .................................................................................................................... III

 

Vision ...................................................................................................................................... iii

Mission Statement ................................................................................................................... iii

Goals ......................................................................................................................................iv

 

DEMOGRAPHIC ANALYSIS......................................................................................................................... IV

 

RECREATION STANDARDS AND NEEDS ASSESSMENT.................................................................................. V

 

Balanced Land Use Guidelines ................................................................................................v

Population-based Recreation Open Space Needs Assessment..............................................v

Recreation Need by Park Classification ..................................................................................vi

 

FACILITY NEED........................................................................................................................................ VII

 

RECOMMENDATIONS............................................................................................................................... VIII

 

LIST OF ILLUSTRATIONS..................................................................................................................XIV

CHAPTER 1 - INTRODUCTION .............................................................................................................. 1

 

MASTER PLAN PROCESS ............................................................................................................................. 2

 

CHAPTER 2 – TOWN-WIDE MASTER PLAN VISION, MISSION, GOALS AND OBJECTIVES................. 5

 

VISION STATEMENT ................................................................................................................................... 5

MISSION STATEMENT................................................................................................................................. 5

GOALS AND OBJECTIVES: ........................................................................................................................... 5

 

Goal 1: To improve the quality of life for community residents. .............................................. 5

Goal 2: Ensure equitable access to safe and attractive parks and facilities that meet

community needs..................................................................................................................... 6

Goal 3: Actively pursue adequate open space for future recreation facilities. ........................ 8

Goal 4: To preserve and enhance the social and ecological environment for Township

residents. ............................................................................................................................... 10

Goal 5: Implement and update the Parks and Recreation Master Plan (PRMP) so it remains

a dynamic guide for the Park and Recreation Department. .................................................. 11

Goal 6: Management of the park system to the highest standards....................................... 12

 

CHAPTER 3 – RELATIONSHIPS TO OTHER PLANS................................................................................ 13

 

2003 MASTER PLAN REEXAMINATION REPORT ........................................................................................ 13

STATE DEVELOPMENT AND REDEVELOPMENT PLAN ................................................................................ 16

 

Planning Areas ...................................................................................................................... 16

 

STATEWIDE COMPREHENSIVE OUTDOOR RECREATION PLAN (2003)........................................................ 18

 

Land Preservation.................................................................................................................. 19

Recreation ............................................................................................................................. 19

Greenways............................................................................................................................ 20

 

Table of Contents

PENNONI ASSOCIATES INC.

Consulting Engineers

 

xii

 

Partnerships.......................................................................................................................... 20

Stewardship ........................................................................................................................... 20

 

PEQUANNOCK OPEN SPACE AND RECREATION PLAN................................................................................ 22

AQUATIC PARK MASTER PLAN................................................................................................................. 22

 

CHAPTER 4 – RECREATION STANDARDS AND NEEDS ASSESSMENT.................................... 25

 

INTRODUCTION ........................................................................................................................................ 25

BALANCED LAND USE GUIDELINES.......................................................................................................... 25

POPULATION-BASED RECREATIONAL OPEN SPACE NEEDS ASSESSMENT.................................................. 26

 

Park Classifications ............................................................................................................... 26

Recreation Need by Park Classification ................................................................................ 47

 

DEMOGRAPHIC ANALYSIS........................................................................................................................ 49

 

Population............................................................................................................................. 50

 

Population total.................................................................................................................... 50

Population density ................................................................................................................. 51

Housing................................................................................................................................. 51

Education.............................................................................................................................. 52

Income.................................................................................................................................. 52

 

FACILITY NEED........................................................................................................................................ 53

 

CHAPTER 5 – INVENTORY AND ANALYSIS OF EXISTING RESOURCES ................................ 57

 

PROCESS .................................................................................................................................................. 57

 

GIS Mapping......................................................................................................................... 57

Site Visits ............................................................................................................................... 57

 

PEQUANNOCK TOWNSHIP PARK LANDS.................................................................................................... 57

 

Aquatic Park .......................................................................................................................... 59

Cherry Street Park................................................................................................................. 59

Foothills Park ......................................................................................................................... 60

Greenview Park ..................................................................................................................... 60

Hidden Cove.......................................................................................................................... 61

Hillview Fields ........................................................................................................................ 62

Lyman Park........................................................................................................................... 62

Lyon Park.............................................................................................................................. 63

Meyers Brook......................................................................................................................... 63

Mountainside Park................................................................................................................. 64

Pequannock Valley Park ....................................................................................................... 64

Riverside Park ....................................................................................................................... 65

Rockledge Park ..................................................................................................................... 65

Town Hall Field...................................................................................................................... 66

Washington Park ................................................................................................................... 66

Woodland Lake...................................................................................................................... 67

 

PEQUANNOCK TOWNSHIP BOARD OF EDUCATION LANDS......................................................................... 68

OTHER RECREATION OPPORTUNITIES ....................................................................................................... 68

NATURAL RESOURCES .............................................................................................................................. 68

 

New Jersey Landscape Project ............................................................................................. 68

Environmental Resource Inventory ....................................................................................... 70

Vegetation and Wildlife.......................................................................................................... 74

Existing Parks Developable Lands........................................................................................ 74

 

AIR QUALITY........................................................................................................................................... 75

NOISE LEVELS ......................................................................................................................................... 75

CONTAMINATED SITES............................................................................................................................. 75

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

xiii

 

CONNECTIVITY OF OPEN SPACE SYSTEM.................................................................................................. 76

 

CHAPTER 6 – BENCHMARK TO SIMILAR RECREATION SYSTEMS..................................................... 103

 

CHAPTER 7 – ACQUISITION, CAPITAL IMPROVEMENT AND MAINTENANCE RECOMMENDATIONS

 

................................................................................................................................................................... 105

 

APPENDIX A – ESTIMATES OF PROBABLE COSTS .............................................................................. 121

 

Table of Contents

PENNONI ASSOCIATES INC.

Consulting Engineers

 

xiv

 

LIST OF ILLUSTRATIONS

 

List of Figures

 

1. Pequannock Township location in Morris County showing related open waters............ i

2. Pequannock Township location in Morris County showing related open waters............1

3. Township Park and Board of Education facility locations.................................... 57

4. Meadow area in Aquatic Park utilized as a circular track by ATVs. ........................ 59

5. Forested area in Aquatic Park.................................................................... 59

6. Waterway in Aquatic Park. ....................................................................... 59

7. Open play area in Foothills Park. .............................................................. 60

8. Sledding at Foothills Park. ........................................................................ 60

9. Playground at Foothills Park...................................................................... 60

10. Greenview Park soccer/lacrosse field. ......................................................... 61

11. Greenview Park softball/little league field. ................................................... 61

12. Greenview Park tennis courts and attendant station......................................... 61

13. Greenview Park playground area. ............................................................... 61

14. Greenview Park restroom facility................................................................ 61

15. Hillview Field softball/little leaguer field. .................................................... 62

16. Lyman Park clearing and playground in trees.................................................. 63

17. Hampton Avenue access to Lyman Park. ....................................................... 63

18. Residential out-parcels in Lyman Park.......................................................... 63

19. Lyon Park playground equipment................................................................ 63

20. View from Mountainside Park. ................................................................... 64

21. Trail and marking at Mountainside Park. ....................................................... 64

22. Mountainside Park camp area. ................................................................... 64

23. Pequannock Valley Park swimming. ............................................................. 65

24. Members entering PV Park. ....................................................................... 65

25. PV Park picnic area with lake in the background. ............................................ 65

26. Town Hall baseball field. ......................................................................... 66

27. Town Hall basketball courts. ..................................................................... 66

28. Washington Park southern ball field. ........................................................... 66

29. Township DPW dumping area in Washington Park............................................. 67

30. Washington Park concessions building. ......................................................... 67

31. Washington Park northern ball field............................................................. 67

32. Woodland Lake boat launch and gravel parking area......................................... 67

33. Trail along a portion of Woodland Lake ........................................................ 67

34. Woodland Lake...................................................................................... 67

 

List of Maps

 

1. Context Map...........................................................................................3

2. Park and School Locations ........................................................................ 33

3. Mini Parks............................................................................................ 35

4. Neighborhood Parks ................................................................................ 37

5. School Parks ......................................................................................... 39

6. Community Parks ................................................................................... 41

7. Sports Complex ..................................................................................... 43

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

xv

 

8. Natural Resource Areas............................................................................ 45

9. Population Density (2000)......................................................................... 55

10. N.J. Landscape Project – Forest ................................................................. 79

11. N.J. Landscape Project – Grassland ............................................................. 81

12. N.J. Landscape Project – Emergent Wetlands ................................................. 83

13. N.J. Landscape Project – Forested Wetlands .................................................. 85

14. N.J. Landscape Project – Wood Turtle Habitat ................................................ 87

15. Geology Map......................................................................................... 89

16. Soils................................................................................................... 91

17. Hydrology ............................................................................................ 93

18. Flood Hazard Areas................................................................................. 95

19. Groundwater Recharge ............................................................................ 97

20. Aquifers Map ........................................................................................ 99

21. Land Cover (2002) .................................................................................101

22. Aquatic Park Concept Plan.......................................................................121

23. Foothills Park Concept Plan .....................................................................123

24. Rockledge Park Concept Plan ...................................................................125

25. Washington Park Concept Plan..................................................................127

 

List of Tables

 

1. Parks by classification, standards and deficiencies / surplus ................................ iv

2. Parks by classification, standards and deficits /surplus ..................................... 47

3. Pequannock Township Population Trends ...................................................... 50

4. Pequannock Township Age Cohort Trends...................................................... 50

5. Pequannock Township Age Cohort Trends as a Percent of the Total Population......... 51

6. Facility Amenities Matrix.......................................................................... 58

7. Environmental factors effecting park land development .................................... 75

8. Benchmark community’s recreation amenities...............................................103

9. Facility Strategy and Implementation Plan ...................................................119

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Chapter 1 - Introduction

 

Pequannock Township is located in the northeast corner of Morris County. It is

bounded on the east by the Pompton and Ramapo Rivers. The confluence of the

Pequannock, Ramapo and Pompton Rivers is located in Aquatic Park in the northeast

corner of the Township (see Figure1 and Map 1).

The fertile valley at this confluence

drew settlers, circa 1700, who farmed

all types of vegetables, flax and raised

livestock. Many types of mills were

built for processing of the farming

products. In 1740 Pequannock

Township was formed by the General

Session of Peace. The initial

incorporation of Pequannock Township

was 74,000 acres. Succession from the

Township began in 1844. By the 1920’s

the current community of 7.04 square

miles, which consists of Pequannock

and Pompton Plains, was all that

remained as Pequannock Township

(Pequannock Township Master Plan, p.

10-12).

 

Figure 2 ~ Pequannock Township location in Morris

County showing related open waters.

 

Pequannock Township has 646.6 acres

of open space land utilized for park

and recreation purposes (see Map 1). Twenty four acres (24-acres) of two parks,

Rockledge and Cherry Street parks, remain undeveloped. The developed parks provide

a variety of recreational opportunities ranging from hiking, playgrounds, athletic fields

and courts, picnic areas, lake swimming, boating, fishing and camping.

This Town-wide Park and Recreation Master Plan (Master Plan) evaluates the number

and quality of facilities provided to Pequannock Township residents against the

anticipated needs and provides recommendations for improvements and acquisitions to

meet the anticipated demand for recreational facilities in the Township.

A master plan is an important tool developed to manage a study area and guide its

future. A master plan takes into account not only the physical environment, but also

the economic and social aspects that have impacts on the study area’s growth and

management.

The purpose of this master plan is to provide a framework, or roadmap, for the

restoration and future improvements within South Mountain Reservation. The master

plan provides for responsible stewardship of valuable recreational, ecological, social,

and historic resources amidst a suburban environment. Goals are understood as a part

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

1

 

Chapter 1 - Introduction

PENNONI ASSOCIATES INC.

Consulting Engineers

 

2

of the process. They are tested against historic, current and anticipated conditions

and needs. From this process a series of recommendations were developed for

implementation to address the identified needs.

The Master Plan is a living document and should be continuously consulted and

updated as improvements are completed and as the residents interests change.

 

MASTER PLAN PROCESS

 

The Master Plan process began with the inventory and analysis of Pequannock

Township’s existing resources. This includes site visits to the existing parks to

evaluative their facilities and natural resources by sight. The recourses evaluated

included athletic fields, picnic areas, roadways, parking areas, trails, buildings,

structures, ponds/lakes and furnishings.

On-site investigations were conducted from June 2006 to November 2006 to observe

general conditions, take measurements, photographs and verify locations. Field data

was combined with information from New Jersey Department of Environmental

Protection (NJDEP), New Jersey Geologic Survey, New Jersey Department of

Transportation and the New Jersey Image Warehouse.

Projected capital improvement plans were reviewed. This included the Aquatic Park

Master Plan. There were no past capital improvement plans identified. A needs

assessment was developed speaking with stakeholders, Township staff and

administration and evaluating the number and quality of the existing facilities against

the anticipated population. The recreation and leisure facilities provided by

Pequannock Township were evaluated against similar communities in Morris County

and the neighboring municipalities.

Recommendations were developed from the synthesis and analysis of all of this

information. These include acquisition opportunities and capital improvements and

prioritization of the identified tasks. Finally a 10-year capital improvement plan was

recommended.

 

Pequannock Township

Recreation Master Plan

 

Context Map

Map 1

 

Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Mountainside Park Aquatic Park

Greenview Park

Woodland Lake

Lyman Park

Foothills Park

Rockledge Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

MORRIS

PASSAIC

 

I-287

 

NJ 23

I-287

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

US 202

CUTLESSRD

BEAVER BROOK RD

HAUL RD

MORRIS COUNTY 660

MOUNTAIN AVE

RYERSON RD

WEST PARKWAY

MANDEVILLE AVE

PASSAIC COUNTY 6892

MORRIS COUNTY 680

RIVERDALE RD

MORRIS COUNTY 655 A

MORRIS COUNTY 651

HOPPER AVE

MORRIS COUNTY 694

ROUTE 504

ROUTE 511 ALTERNATE

ROUTE 504

US 202

 

CUMBERLAND

 

OCEAN

SUSSEX

ATLANTIC

BURLINGTON

MORRIS

SALEM

WARREN

MONMOUTH

CUMBERLAND

HUNTERDON

BERGEN

MIDDLESEX

CAPE MAY

SOMERSET

MERCER

CAMDEN

GLOUCESTER

PASSAIC

ESSEX

UNION

HUDSON

 

I-78

I-80

I-295

I-195

GARDEN STATE PARKWAY

I-287

I-280

NEW JERSEY TURNPIKE

I-95

I-676

NEW JERSEY TURNPIKE

I-287

I-95

 

3

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

5

 

Chapter 2 – Town-wide Master Plan

Vision, Mission, Goals and Objectives

 

VISION STATEMENT

 

To provide a well rounded recreation and leisure experiences for all members

of the community.

 

MISSION STATEMENT

 

The Township will meet the physical, mental, cultural and social needs of

Pequannock residents by providing the best possible overall park system through

programs, services, facilities and structures and by preserving and developing new and

existing lands and their improvements.

 

GOALS AND OBJECTIVES:

 

Goal 1: To improve the quality of life for community residents.

 

Objective 1.1: Enhance community spaces such as parks, streetscapes and

cultural resources.

 

? Statement: Parks, streetscapes cultural resources and environmental

resources help define the character of Pequannock Township. The

Department of Parks and Recreation through the Director in concert with

provide Township agencies and organizations will strive to improve and

maintain these vital resources.

Objective 1.2: Provide community activities and programs.

 

? Statement: Providing community activities and programs are essential to

encourage healthy active living. The more active Pequannock residents are

the happier and more peaceful residents will be. Healthcare costs will also

be reduced. The Department of Parks and Recreation through the Director

will educate the Pequannock children and adults about healthy alternatives

for their eating and recreation habits and provide them a variety of

recreation opportunities.

Objective 1.3: Address public safety.

 

? Statement: The variety of recreation opportunities should be safe to

participate in. The Department of Parks and Recreation, through the

Director and working with other municipal departments and organizations,

will provide recreation opportunities that are as safe as possible taking into

consideration the inherent risks associated with some recreation

 

Chapter 2 – Town-wide Master Plan Vision,

Mission, Goals and Objectives

PENNONI ASSOCIATES INC.

Consulting Engineers

 

6

opportunities. The facilities will be monitored and maintained in that their

use is safe.

 

Goal 2: Ensure equitable access to safe and attractive parks and

facilities that meet community needs.

 

Objective 2.1: Enhance/renovate existing facilities to maximize optimal usage.

 

? Statement: Existing park lands and structures are a valuable resource to

the Township residents and should be utilized to their highest and best use.

The existing facilities should be continuously evaluated to improve

efficiencies and such improvements should be implemented. The

Department of Parks and Recreation through the Director will identify

possible efficiencies and work towards implementing them as recommended

in the Master Plan.

Objective 2.2: Provide a system of community parks with balanced recreation

opportunities directed to all residents.

 

? Statement: A variety of recreation and leisure opportunities, including

passive and active programs, are important to provide for residents. The

Township should not loose sight of the importance of passive recreation

such as hiking, boating, fishing, gardening, nature study, etc. The

Department of Parks and Recreation through the Director will continue to

provide the varied recreation and leisure opportunities to Township

residents.

Objective 2.3: Increase the number of active recreation facilities available for use

by the Township residents.

 

? Statement: Participation in active recreation continues to grow. Sports are

being played in two or more seasons when they traditionally were played in

one. New sports are gaining in popularity with consistent increases in

participation. Residents are participating in both recreational leagues and

traveling leagues. All of these factors lead to the need for additional fields

to support the interest by the Township residents. The Department of

Parks and Recreation through the Director will work with the Board of

Education to strive to increase usage of their facilities through joint

venture projects as well as acquisition of additional lands that support

active recreational use.

Objective 2.4: Collaboration and partnership with local groups and surrounding

communities and groups for use of facilities and community programs.

 

? Statement: The Township of Pequannock has a small land area with many

of its lands ecologically sensitive (wetlands, steep slopes, floodway). This,

factored with the active participation in the recreation programs offered in

Town, makes it difficult the Township to be the sole provider to meet the

demand. The Department of Parks and Recreation through the Director will

continue to work with the Board of Education and local community groups

who provide supporting programs. The Department will also open dialogues

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

7

with local municipalities to evaluate the feasibility to share recreation

facilities. The Department of Parks and Recreation through the Director will

develop a plan to coordinate all recreational opportunities (organizations)

within the Township and neighboring communities.

Objective 2.5: Balance the pro vision of open space with other land uses.

 

? Statement: Land is a limited resource. This is even more evident in

Pequannock Township with the extensive wetlands, floodway and floodplain

within the Township. Other possible land uses should be balanced with the

vision of open space for recreation and resource conservation. When this

is done the value of open space and resource conservation can be seen as

an economic benefit similar to previously typical forms of land

development. The Department of Parks and Recreation through the

Director will work with the Open Space Committee to evaluate possible

land acquisitions for their use as a recreational resource. The Department

of Parks and Recreation through the Director will present possible lands for

acquisition to the Open Space Committee.

Objective 2.6: Expand the local trail system to a local greenway network linking

the Township park system, schools, cultural resources and business district for safe

pedestrian access to all facilities.

 

? Statement: A greenway system throughout the Township would provide the

opportunity to link the natural environment as well as the human

environment together. Natural habitat becomes more valuable for flora

and fauna when they are contiguous and not isolated pockets. Similarity,

parks and other open space become an even more valuable resource when

they are linked together through a greenway system. The greenway would

provide opportunities to safely travel throughout Town using alternative

means of travel. The Department of Parks and Recreation through the

Director will work with the Open Space Committee and administration in

developing a greenway network throughout the Township.

Objective 2.7: Link the existing Township trail system to Morris County’s trail

system.

 

? Statement: Linking the existing trail system and future greenway network

to Morris County’s trail system will further expand the alternative travel

and recreation opportunities for Township residents. The Department of

Parks and Recreation through the Director will actively pursue linkages to

the Morris County trail system.

Objective 2.8: Link Township bike path to Morris County’s bike paths.

 

? Statement: Similar to linking the trail system, linking the existing bike

paths to Morris County’s bike paths will further expand the alternative

travel and recreation opportunities for Township residents. The

Department of Parks and Recreation through the Director will actively

pursue linkages to the Morris County bike paths.

 

Chapter 2 – Town-wide Master Plan Vision,

Mission, Goals and Objectives

PENNONI ASSOCIATES INC.

Consulting Engineers

 

8

Objective 2.9: Update and implement the Aquatic Park Master Plan in

collaboration with neighboring communities.

 

? Statement: Aquatic Park is a valuable resource largely inaccessible to

Township residents. A master plan for the property was previously

completed and should be updated based upon new NJDEP regulations and

recent findings. The Department of Parks and Recreation through the

Director will update the master plan and work with neighboring towns and

the administration in implementing the updated master plan.

Objective 2.10: Provide a recreation center that would address the expanding

indoor programming needs for day care, gym, weight room, large community

meeting room, etc.

 

? Statement: Indoor recreation programs are held within the local schools.

While this is a good partnership, the available hours are decreasing due to

increasing school programming. The recreation programs are consistently

loosing space and time while the demand continues to rise. The demand

currently exists to support a building dedicated to recreation programming.

The Department of Parks and Recreation through the Director will work

with Township committees, boards and administration to implement a new

recreation center.

Objective 2.11: Provide for specific recreation opportunities (i.e. camping,

fishing, boating, fitness trails).

 

? Statement: Pequannock Township’s location at the base of the Waghaw

Mountains and the confluence of two rivers gives Township residents the

opportunity for recreation experiences unique to the Township. These

opportunities should continue to be provided and emphasized as important

to the Pequannock recreational experience. The Department of Parks and

Recreation through the Director will continue to provide and support these

unique, specific recreation opportunities.

Objective 2.12: Support cooperative efforts between the Historic Preservation,

Open Space, Shade Tree and Environmental Commissions.

 

? Statement: These Commissions and the Park and Recreation Department

have similar and sometimes overlapping goals. These groups should

cooperatively update each other and work together to provide the most

cohesive and efficient results for Township residents. The Department of

Parks and Recreation through the Director will actively work with the other

Commissions to support their efforts and with an emphasis on the

relationship to providing recreation services to the local community.

 

Goal 3: Actively pursue adequate open space for future recreation

facilities.

 

Objective 3.1: Update the Township’s recreation and open space inventory (ROSI)

to include all parks and Township owned open space and submit to Green Acres.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

9

 

? Statement: Lands listed on the ROSI are preserved as open space in

perpetuity. By listing all open space lands, not only parklands, these lands

will be available for use by Pequannock residents for generations to come.

The Department of Parks and Recreation through the Director will update

the ROSI immediately to include existing open space lands and will continue

to update in the future when additional lands are added to the Township’s

open space system.

Objective 3.2: Actively pursue new Open Space lands for recreation

 

? Statement: The Department of Parks and Recreation through the Director

will work with the Township Open Space Committee and administration to

actively pursue Open Space lands. Immediate action will be to further

evaluate the options for the lands identified for acquisition for recreation

use in the Open Space Plan and as recommended within this report.

Objective 3.3: Engage the landowners of agricultural lands to participate in New

Jersey’s farmland preservation program.

 

? Statement: The farmland (farmland assessed properties) within

Pequannock Township is one of the major defining elements of the

Township’s character. To loose these lands to development would change

the Township’s character forever. The Department of Parks and Recreation

through the Director will work with the Open Space Committee and

administration to open dialogues with the farm owners to try to gain

interest in the States’ farmland Preservation program.

Objective 3.4: Follow-up with the proposal for the Pia Costa tract to act as a

wetlands mitigation bank.

 

? Statement: The Pia Costa tract is a valuable ecological resource as there

are significant wetlands on the property and there have been threatened

and endangered plant and animal species sited on the property. It also acts

as flood storage for the Township. With the approval of this property as a

receiving property as a wetlands mitigation bank the wetlands would be

preserved, restored and new wetlands created. The Department of Parks

and Recreation through the Director will work with the Open Space

Committee and the administration to support this property acting as a

wetlands mitigation bank.

 

Chapter 2 – Town-wide Master Plan Vision,

Mission, Goals and Objectives

PENNONI ASSOCIATES INC.

Consulting Engineers

 

10

 

Goal 4: To preserve and enhance the social and ecological

environment for Township residents.

 

Objective 4.1: Preservation of environmentally sensitive areas. Coordinate these

efforts with adjacent communities.

 

? Statement: Disturbance of ecologically sensitive lands has a negative

impact on the quality of life of Township residents as well as the flora and

fauna in the Township. Disturbance of steep slopes of the Waghaw

Mountains effects soil stability, disturbance of wetlands effects water

quality and disturbance of floodways affects flood limits. The ecological

environment is not limited by governmental boundaries. It is important,

therefore, for all governing bodies that are spanned by the resource to

work together to preserve the resource. The Department of Parks and

Recreation through the Director will actively work with governing boards,

commissions and conservancy groups of Pequannock Township and

neighboring municipalities and county to preserve the ecological resources

in the area.

Objective 4.2: Use environmentally sensitive areas as educational resources.

 

? Statement: The numerous ecological resources in the Township provide a

unique opportunity to draw the Township residents back to nature. There

are spectacular views from Mountainside Park, possible siting of a state

threatened species, the wood turtle, at Rockledge Park and numerous

opportunities for nature study at Cherry Street Park, Aquatic Park and

others. The Department of Parks and Recreation through the Director will

actively pursue partnership opportunities to thoughtfully develop

environmentally sensitive lands in accordance with regulations and provide

programs with the Board of Education that can meet NJ core curriculum

standards.

Objective 4.3: Preserve historically significant structures and adjoining lands.

Provide a link between the cultural resources to the Township park system.

 

? Statement: Pequannock Township retains is character from its colonial

roots and has numerous historical structures that remain from that time.

Connecting these sites to the park and open space system can bring

opportunities to educate the public about local heritage and active

recreation at the same time as they travel from one site to another. The

Department of Parks and Recreation through the Director will support the

cultural resources in the Township and work to create a greenway system

that includes the Township’s cultural resources.

Objective 4.4: Educate the public about park resources and park stewardship.

 

? Parks help citizens join together to make their communities better by

encouraging them to participate in park planning and management. Ties

among community residents can be built and strengthened by bringing

people together, including those who are otherwise divided by race or

class, and by helping them work together on common projects. The

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

11

Department of Parks and Recreation through the Director will continue to

support community involvement in the planning and management of their

parks.

Objective 4.5: Work in conjunction with state open space preservation goals.

 

? Open space systems become stronger and more beneficial to local and

regional residents the more connections there are to other systems.

 

Neighboring towns should have a cohesive network that also connects to the

larger county network then the state network. The Department of Parks and

Recreation through the Director will meet or exceed the preservation goals

outlined by the state by working with the Open Space Committee,

administration and through partnerships.

 

Goal 5: Implement and update the Parks and Recreation Master Plan

(PRMP) so it remains a dynamic guide for the Park and Recreation

Department.

 

Objective 5.1: Pursue funding through grants, loans, gifts and donations to

implement Township PRMP per the recommendations in the Master Plan.

 

? There are many possible partners to provide the recreation resources for

Pequannock residents, many of which were identified in the Pequannock

Open Space and Recreation Plan. The Department of Parks and Recreation

through the Director will work with the administration in pursuing

alternative funding sources to implement the CRMP.

Objective 5.2: Develop capitol improvement plans for 1, 3, 5, and 10 years.

 

? Statement: Priorities for improvements and capital expenditures need to

be set to allow for proper planning of expenditures. The Department of

Parks and Recreation through the Director will develop and update capitol

improvement plans for the years noted.

Objective 5.3: Solicit form the community their program and activities wants and

needs and when possible, implement them.

 

? Statement: Recreation trends change over time. The CRMP should be

updated approximately once every five years to verify any changes that

should be made to support the current way residents recreate. The

Department of Parks and Recreation through the Director will work with the

community when updating the master plan.

 

Chapter 2 – Town-wide Master Plan Vision,

Mission, Goals and Objectives

PENNONI ASSOCIATES INC.

Consulting Engineers

 

12

 

Goal 6: Management of the park system to the highest standards.

 

Objective 6.1: Raise the standards of the maintenance operations for all facilities.

 

? Statement: When a facility is well maintained it is well respected by the

user and receives more respect and less vandalism, even if it is only in the

form of trash left on the ground. By constantly striving to improve

maintenance the Township staff as well as residents can take pride in the

service that is provided. The Department of Parks and Recreation through

the Director will strive to maintain all facilities to the highest standards

possible. The Department of Parks and Recreation through the Director will

develop and implement a comprehensive maintenance schedule for each

facility.

Objective 6.2: Provide tools and performance standards to manage the

responsibility, authority and accountability of the Park and Recreation Department

and its operations.

 

? The Director of the Park and Recreation Department is solely responsible

and has full control of the Department’s functions and operations allowing

for efficiency and full accountability, however, the restructuring and

financial operations of the Department would enable the Director to fully

utilize the tools necessary to provide services to the Department’s

constituents. The director will propose changes to the administration

consistent with acceptable budgeting and accounting standards to provide a

more efficient functioning of the department.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

13

 

Chapter 3 – Relationships to Other Plans

 

In the preparation of the Recreation Master Plan for Pequannock Township, many

previously completed reports were analyzed and taken into consideration. These

reports include the 2003 Master Plan Reexamination Report, the Highlands Council

Draft Regional Master Plan, The Pequannock Open Space Plan and the Aquatic Park

Master Plan. The recommendations set forth in the Recreation Master Plan strongly

reflect the goals set forth in these documents.

 

2003 MASTER PLAN REEXAMINATION REPORT

 

In 2003 a reexamination report for Pequannock Township’s Master Plan was

completed. The purpose of this document was to reevaluate the goals identified

within the Master Plan to ensure that they still reflected current community goals.

Furthermore, it identifies new goals that may have developed since the initial release

of the Master Plan and previous reexamination reports. The implementation of a path

and trail system to better connect the townships parks and open space as well as an

initiative to provide additions and improvements to the current park facilities are the

two major goals set forth in the 2003 Master Plan Reexamination report that address

the deficit of recreational space that currently exists within the Township. Specific

goals listed in the Reexamination Report related to active and passive recreation and

leisure include:

 

? Protect the views of the mountains by locating development in areas on or

around the mountains so as not to disturb these views. Emphasize

collaborative work with the Borough of Kinnelon to help preserve this area.

 

? Promote a Path and Trail System that will utilize existing trails and, with new

links, will connect the Township’s parks and open spaces.

 

Solicit an ANJEC grant to convert the railroad right-of-way into a bike path.

 

Participate in the Morris Land Conservancy’s Partners for Greener

Communities.

 

Develop conservancy trail initiatives with Pequannock Township see the

 

Open Space and Recreation Plan, specifically regarding bike lanes.

 

? Limit development along rivers, streams and ditches and around lakes so as to

create buffers, and where possible, greenways and paths. Coordinate the

conservation of these areas with adjacent communities utilizing conservation

easements and other land protection mechanisms.

 

Aquatic Park along the Pequannock River provides a greenway and path

along the Pequannock River. Along the length of the river corridor, the

severity of the wetlands and floodplains has caused the area to experience

limited development. In order to protect and enhance the river, its banks,

and the floodplains, an overall plan for river from access and community

 

Chapter 3 – Relationships to Other Plans

PENNONI ASSOCIATES INC.

Consulting Engineers

 

14

use should be created. The Township restricts development of

environmentally sensitive lands by restricting construction in flood plains

and enforcing wetland protection laws.

 

? Preserve and protect the area of confluence of the Pequannock and Wanaque

Rivers which include numerous islands and coordinate these efforts with

adjacent communities.

 

See the Open Space and Recreation Plan for more details.

 

? Protect areas of steep slopes and scenic stream corridors of the Waughaw

Mountains.

 

? Promote clean air.

 

? Support the implementation of the recommendations of the Department of

Parks and Recreation regarding additions and improvements to park facilities.

 

The Township of Pequannock has an Open Space Tax for the purchase of

open space/recreation lands, recreation upgrades of existing facilities and

purchase of equipment.

 

? Seek the implementation of a path and trail system through a variety of land

protection mechanisms and public access programs.

 

ANJEC grant application

 

The Open Space and Recreation Plan lists a number of possible

protection mechanisms.

 

? Protect and safeguard the aquifer recharge areas and wells through appropriate

zoning and enforcement.

 

? The Township Zoning Ordinance provides zoning safeguards to protect the

aquifer recharge areas and wells of the Township through its regulation of

permitted and prohibited uses.

 

? Continue to implement floodplain management policies, regulations and

programs aimed at promoting safety and preventing flood damage.

 

? Preserve the Pia Costa tract’s floodwater retention capability.

 

? Pequannock Township is critically situated in a plain at the base of the NJ

Highlands at the confluence of the Pompton, Pequannock, and Ramapo Rivers.

The community is ideally located and is important for the linkage and transition

it provides between the rural Highlands communities and suburban

Passaic/Morris County communities. The area is environmentally significant for

the flood plain and water resources is affords, but also for the extensive

wetlands, and wildlife habitat and linkages adjacent to the river that is

provides. Pequannock Township must make it a priority to protect these areas,

expand open space opportunities and provide essential linkages to Township

and regional trails through improvements to Aquatic Park and along the river.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

15

 

The river and lands adjacent to the river also offer a unique opportunity to both

the community and the region. As such as Aquatic Park along the Pequannock

River are ideally located, but have no parking, signage or improvements. Along

the length of the river corridor, the severity of the wetlands and floodplains has

caused the area to experience limited development. In order to protect and

enhance the river, its banks, and the floodplains, and overall plan for riverfront

access and community use should be created. Such improvements to consider

include property acquisition, trial linkages, and possible playfield.

 

Highlands Council Draft Regional Master Plan

 

In August 2004, the New Jersey Legislature enacted the Highlands Water Protection

and Planning Act (Highlands Act) with the goal of protecting and planning for a region

that supplies drinking water for more than 5.4 million New Jersey residents. As a

guide to ensure this goal is met the Highlands Council has issued a draft Regional

Master Plan for public comment before a final plan is adopted. The Highlands region,

which consists of 860,000 acres in 88 municipalities, is divided into two classifications

that are determined by an areas specific level of sensitivity and ecological

significance. The more sensitive areas are defined as Preservation Areas while the less

critical areas are defined as Planning Areas. All of Pequannock Township falls within

the jurisdiction of the Highlands Act. Pequannock Township north of Interstate 287

including Mountainside Park is within the Highlands Preservation area while the

remainder of the Township falls within the Highlands Planning Area.

Land that falls within the Preservation Areas must abide by the regulations of the

Highlands Water Protection and Planning Act. The Planning Areas, on the other hand,

are not required to comply with these regulations although it is strongly

recommended. In fact many municipalities are providing incentives to do so.

Furthermore, these areas each have specific planning goals. Of particular importance

is that the Preservation Areas and Planning Areas share the common goal of preserving

outdoor recreation, hunting and fishing, on publicly owned land. For a complete list

of goals and requirements please refer to the Highlands Council Draft Regional Master

Plan. Another feature of the Highlands Council Draft Regional Master plan is the Land

Use Capability Map which breaks the highlands region down into different zones that

indicate the type of development the land can support. The Land Use Capability Map is

based on an analysis of natural resources, existing development, infrastructure, and

agricultural activities. The map establishes three major geographic zones that overlay

municipal zoning, each with its own criteria and standards. See below for a description

of each:

 

The Conservation Zone consists of areas with significant agricultural lands

mixed with important environmental features that should be preserved when

possible. There are no lands within Pequannock Township classified as

Conservation Zones.

 

The Protection Zone consists of environmentally important lands that are

critical to maintaining water quality, quantity, and other significant ecological

processes. Standards in the zone prohibit the disturbance of natural resources

 

Chapter 3 – Relationships to Other Plans

PENNONI ASSOCIATES INC.

Consulting Engineers

 

16

or expansion of infrastructure. Public land acquisition is a priority in the

Protection Zone.

Within Pequannock Township the Protection Zone includes Mountainside Park

and the western portion of the Township whose limits appear to conform to the

eastern wetlands boundaries, Aquatic Park and the Pia Costa Tract.

 

The Planned Community Zone consists of areas with existing concentrated

development. These areas are less environmentally constrained, and, with

planning, may support development in a manner and intensity desired by the

municipality. Emphasis will be on increasing land use efficiency, encouraging

the use of previously developed lands through techniques such as

revitalization, adaptive reuse, in fill, and property assemblage. In addition to

zone standards, site specific standards may apply, reflecting the presence of

such natural features as streams or steep slopes. The remainder of

Pequannock Township is located within this zone.

 

STATE DEVELOPMENT AND REDEVELOPMENT PLAN

 

The purpose of the State Development and Redevelopment Plan (State Plan) is to:

 

Coordinate planning activities and establish Statewide planning objectives in the following areas: land use,

housing, economic development, transportation, natural resource conservation, agriculture and farmland

retention, recreation, urban and suburban redevelopment, historic preservation, public facilities and services,

and intergovernmental coordination (N.J.S.A. 52:18A-200(f)).

The State Plan identified Parks and Natural Areas as a public investment specifically

for resource preservation and the provision of recreational opportunities. Parks and

Natural Areas fulfill a broad range of functions along continuum from resource

conservation to active recreation.

With the delineation of Parks and Natural Areas, the State Plan’s intention is to

protect critical habitats and resources, provide recreational opportunities and create a

connected system of open lands for posterity. According to the map titled “Critical

Environmental Sites and Historic and Cultural Sites” there is a ring of critical

environmental lands that appear to stretch from Mountainside Park along the northern

Township boundary to and including Aquatic Park. Critical Environmental sites are

also located along the East Ditch.

 

Planning Areas

 

The State Development and Redevelopment Plan (1) provides a balance between

growth and conservation by designating planning areas that share common conditions

with regard to development and environmental features. Those that are found within

Pequannock Township include:

 

Areas for Growth: Metropolitan Planning Areas Planning Area 1 in the eastern

portion of the Township.

 

Areas for Limited Growth: Fringe Planning Areas Planning Area 3 is a finger

centrally located pointing southwest to the southern township boundary and

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

17

Environmentally Sensitive Planning Areas Planning Area 5 is within Mountainside

Park area and the westernmost Township boundary. In these planning areas,

planning should promote a balance of conservation and limited growth—

environmental constraints affect development and preservation is encouraged

in large contiguous tracts.

 

Areas for Conservation: Environmentally Sensitive Planning Areas Planning Area

5 is within Mountainside Park area and the westernmost Township boundary.

 

Planning Area 1 Objectives related to Parks and Open Space includes:

 

? Natural Resource Conservation: Reclaim environmentally damaged sites and

mitigate future negative impacts, particularly to waterfronts, scenic vistas,

wildlife habitats and to Critical Environmental Sites, and Historic and Cultural

Sites. Give special emphasis to improving air quality. Use open space to

reinforce neighborhood and community identity and protect natural linear

systems, including regional systems that link to other Planning Areas.

 

? Recreation: Provide maximum active and passive recreational opportunities and

facilities at the neighborhood, local and regional levels by concentrating on the

maintenance and rehabilitation of existing parks and open space while

expanding and linking the system through redevelopment and reclamation

projects.

 

? Historic Preservation: Encourage the preservation and adaptive reuse of

historic or significant buildings, Historic and Cultural Sites, neighborhoods and

districts in ways that will not compromise either the historic resource or the

area’s ability to redevelop. Coordinate historic preservation with tourism

efforts.

 

Planning Area 3 Objectives related to Parks and Open Space includes:

 

? Natural Resource Conservation: Strategically acquire open space to define

Centers and to maintain contiguous open space corridors that link to other

Planning Areas and Centers.

 

? Recreation: Provide maximum active and passive recreational opportunities

and facilities at neighborhood and local levels by targeting and acquisition and

development of neighborhood and municipal park land within Centers. Provide

regional recreation opportunities by targeting park land acquisitions and

improvements that enhance large contiguous open space systems.

 

? Historic Preservation: Encourage the preservation and adaptive reuse of

historic or significant buildings, Historic and Cultural Sites, neighborhoods and

districts in ways that will not compromise either the historic resource or the

ability of a Center to develop or redevelop. Outside Centers, coordinate

historic preservation needs with open space and farmland preservation efforts.

Coordinate historic preservation with tourism efforts.

 

Chapter 3 – Relationships to Other Plans

PENNONI ASSOCIATES INC.

Consulting Engineers

 

18

 

Planning Area 5 Objectives related to Parks and Open Space includes:

 

? Natural Resource Conservation: Protect and preserve large, contiguous tracts

and corridors of recreation, forest or other open space land that protects

natural systems and sensitive natural resources, including endangered species,

ground and surface water resources, wetland systems, natural landscape of

exceptional value, critical slope areas, scenic vistas and other significance

environmentally sensitive features.

 

? Recreation: Provide maximum active and passive recreational and tourism

opportunities at the neighborhood and local levels by targeting the acquisitions

and development of neighborhood and municipal parkland within Centers.

Provide regional recreation and tourism opportunities by targeting parkland

acquisitions and improvements that enhance large contiguous open space

systems. Ensure meaningful access to public lands.

 

? Historic Preservation: Encourage the preservation and adaptive reuse of

historic or significant buildings, Historic and Cultural Sites, neighborhoods and

districts in ways that will not compromise either the historic resource or the

ability for a Center to develop or redevelop. Outside Centers, coordinate

historic preservation needs with open space preservation efforts. Coordinate

historic preservation with tourism efforts.

 

STATEWIDE COMPREHENSIVE OUTDOOR RECREATION PLAN

 

(2003)

 

A Statewide Comprehensive Outdoor Recreation Plan (SCORP) is produced every five

years to serve as a status report, strategic plan and guide for natural and recreational

resource protection and planning within the State. The major goals of the 2003 SCORP

include preserving open space, promoting the development of parks, implementing

policies consistent with New Jersey’s smart growth principles, supporting open space

initiatives of local government and organizations, and to use funding from open space

programs effectively. Furthermore, the 2003 SCORP presents current information on

the supply, demand and need for recreation and open space in New Jersey.

For purposes of estimating the amount of open space required for recreation purpose,

an

approach referred to as the Balanced Land Use Concept has been determined to be

the

most appropriate for New Jersey. The Balanced Land Use approach is a method of

estimating the amount of recreational land that should be set aside by governments in

New Jersey to provide recreation opportunities for the existing and future residents of

the state. According to these guidelines 3% of the land at a municipal level should be

set aside for recreation.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

19

During the preparation of 2003 SCORP seven issues were identified as being necessary

to meet the current and projected future public open space and recreation needs in

New Jersey. The issues stated in this SCORP related to Pequannock Township are:

 

Land Preservation

 

Open space is an intricate system serving a variety of functions, often

concurrently, which are essential in sustaining and enhancing New Jersey as a

desirable place to live and work. Open space can protect the quality and

quantity of surface and groundwater resources, guide development and growth,

preserve natural and historic resources, shape community character, and

provide land for recreation. Additionally, the economic value and benefits of

open space have been the subject of several studies. From increasing the value

of adjacent properties and generating revenue from recreational activities to

reducing the cost for public services, the economic impact of open space can

be significant.

 

Recreation

 

Recreation providers are finding that while recreation demand is increasing and

contributes significantly to the State’s economy, the benefits it supplies are

not easily dispensed. The demand and need for recreation are being driven

largely by the State’s increasing population. It seems that it is impossible to

build enough soccer fields or softball fields in New Jersey. It also seems

difficult to find a park in the state that does not have a problem with Canada

geese. There is a statewide trend of residents living near parks resisting the

development of recreation facilities, particularly playing fields. Increased

usage translates into greater operational and maintenance costs. Demographic

trends point not only to an increasing population, but also the ongoing aging of

New Jersey’s population.

All of these factors, along with others means that public park and recreation

agencies must continue to provide the programs and facilities to meet an

increasing demand. Annual visitation at state parks tops 15 million and

Monmouth and Somerset counties report annual park attendance of nearly four

million and two million, respectively. At the municipal level, towns struggle

with finding fields for soccer games. That fact and that recreation land often

competes with other land use needs complicates matters even more. It is clear

that the State and local governments must work together to provide for the

parks and recreation needs of its citizens. It is also clear that planning will play

a key role in identifying appropriate lands for recreational development. Local

government open space and recreation plans can guide the acquisition and

development of public conservation and recreation areas to provide a balanced

park system.

 

Chapter 3 – Relationships to Other Plans

PENNONI ASSOCIATES INC.

Consulting Engineers

 

20

 

Greenways

 

Called parkways or greenbelts in the past, greenways have evolved as an

economical and efficient solution to the need for public open space throughout

New Jersey. Greenways can offer close to home recreational activities such as

walking, running, biking and birding. Those associated with water can provide

canoeing and fishing opportunities. Greenways also can protect

environmentally sensitive areas, link public open space areas, provide wildlife

habitat and preserve community character. Rarely does a greenway serve a

single purpose.

The goals of the Garden State Greenways project are to:

 

Protect New Jersey’s natural resources, water quality, and biodiversity.

 

Maintain and enhance large, significant areas of habitat and

environmentally sensitive lands as part of New Jersey’s green

infrastructure.

 

Contain urban sprawl.

 

Link components of the green infrastructure throughout the state to

provide recreational opportunities within walking distance access to

New Jersey residents.

 

Promote public awareness and use of the State’s green infrastructure.

 

Foster coordination and partnerships among state, federal, local and

non-government agencies involved in conservation, recreation and land

use planning efforts.

 

Partnerships

 

It is hard to imagine open space preservation in New Jersey without

partnerships. In fact, it has become common practice to seek partners to

leverage funding, share project responsibilities or assist in land management

activities. The need for agencies and organizations to participate in partnership

projects in New Jersey is great. The benefits are many but there are also

complications. However, time and again, partnerships prove themselves to be

an important strategy to employ and worth the effort. Simply put, some

projects would not be possible without partnerships. Increased data sharing

among governmental jurisdictions and conservation groups would enhance

preservation and planning efforts.

 

Stewardship

 

Both state and local governments are challenged to meet the goal of proper

stewardship of the public’s lands and recreational resources. The State

Department of Environmental Protection manages 64% of all public lands in

New Jersey. Local governments manage 18% of public lands. Though much of

the State land is largely undeveloped, many historic, recreation and education

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

21

facilities are maintained and operated on both state and local lands. Over

many years, funds for the operation and capital needs in recreation areas have

fallen short of the needs. Some local governments use open space taxes for

development and maintenance expenditures associated with their park

systems. In these cases, dedicated funding has given these jurisdictions some

predictability and flexibility to meet the needs to acquire open spaces,

maintain their recreation infrastructure and meet the needs of visitors.

Deferral of capital spending for renovation and rehabilitation can lead to larger

expenses down the road. Some facilities require compliance with disability

access guidelines and some are in need of costly upgrades for environmental

infrastructure projects such as water and sewage systems. Capital needs left

unmet can lead to irreplaceable resource losses, particularly those of historic

significance.

Stewardship at times entails enforcement to protect natural resources. The

increasing popularity of off-road vehicles (ORV) in New Jersey has presented

challenges for the management of public lands and the protection of natural

resources. As ORV ownership has increased in New Jersey and neighboring

states over the past several years, there has been a marked increase in the

unlawful use of these vehicles on public lands. This unlawful usage has caused

extensive damage to sensitive natural areas with no provision for restoration;

has diminished the use and enjoyment of public lands and other natural areas

by other user groups; has diverted resources from other resource protection

priorities; and has created serious risks to ORV users, to the public, and to law

enforcement personnel. By adopting a policy that prohibits ORV use in state

parks, forests and wildlife management areas, and increases fines, together

with increased enforcement, the State has taken an aggressive stance against

unlawful use of ORV on state lands.

Stewardship, however, also involves planning and working with interest groups

to address concerns and find solutions. As part of its ORV policy, the Division of

Natural and Historic Resources will work to develop appropriate recreational

areas for lawful ORV users with the goal of having two new such facilities in

operation by 2005. The New Jersey Trails Council will participate in this effort

by establishing an ORV subcommittee representing a cross-section of interested

environmental, recreational, ORV industry and ORV user groups. No current

state park, wildlife management area or other environmentally sensitive area

will be considered in the site review and selection process.

The Governor’s Council on New Jersey Outdoors has over the years identified a

lack of park operation and maintenance funding as a serious problem

confronting public recreation providers. State public open space and recreation

areas are challenged by rapidly increasing visitation. The Division of Parks and

Forestry has experienced a more than 4.1 million increase in annual visitation

between 1991 and 2001. For those that care about the natural, recreational

and historic resources and for those that have a clear vision of the imperative

to protect open space, it is frustrating to contemplate this question: How can

 

Chapter 3 – Relationships to Other Plans

PENNONI ASSOCIATES INC.

Consulting Engineers

 

22

we spend money to protect more open space when we do not take proper care

of the lands and facilities for which we are already responsible?

The answer is that we must do both – balancing fiscal resources for both

preservation and stewardship needs. Many lands that are in public ownership

require very little, in terms of resources, to manage. Others, particularly the

high recreation use areas of parks and some wildlife management areas, need

substantive fiscal and personnel resources. Public testimony to the Governor’s

Council was critical of both local and state governments’ inadequate attention

to the stewardship of public parks and recreation areas. The need to serve the

public through the protection of open space and maintenance of historic and

recreational resources is a critical quality of life issue for New Jersey residents.

 

PEQUANNOCK OPEN SPACE AND RECREATION PLAN

 

In 1993 an Open Space and Recreation Plan was developed for Pequannock Township.

This document inventoried the natural, historic, and recreation assets of the Township

and provided suggestions to preserve and expand upon these valuable resources.

The need for additional recreational space was strongly emphasized within the

Pequannock Open Space and Recreation Plan. The plan notes that recreation demand

remains strong and continues growing with an increasing number of residents

participating in sports and suggests the acquisition of additional lands to accommodate

this demand.

The recommendations section of this report identifies specific parcels with the

potential for development into athletic fields. In addition to the shortage of athletic

fields and recreation facilities, the report identifies the need to improve access to

existing facilities as well as increase the amount of parking provided. Within our

recommendations we have provided concepts illustrating how this can be

accomplished. Finally, the report recommends the development of a greenway system

connection the Highlands region in the west to the Rivers on the east. This would

provide increased protection against flooding, provide increased recreational

opportunities along the river and create connectivity between existing parcels of open

space. This improved connectivity would make the existing open space much more

function from both an ecological and use perspective.

 

AQUATIC PARK MASTER PLAN

 

Completed in October 2004 by Burgis Associates, the Aquatic Park Master Plan put

forth several goals for the park. These goals included creating a connection with

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

23

existing open space resources in the region, provide unique recreational opportunities

for a diversity of users, ensuring the continued conservation of this ecologically

sensitive area and to provide educational opportunities relation to the environment

and habitat such as wildlife viewing areas. Recommendations for Aquatic Park put

forth in the master plan included improved accessibility and parking, a park

gateway/information kiosk, an amphitheater, a meadow habitat region, an aquatic

habitat region and a river trail, and a woodland habitat region.

The Aquatic Park Master Plan addresses the 40 acres of Pequannock owned land.

Pequannock Township, however, has the rights to develop and manage the 40 acres of

Aquatic Park lands owned by Morris County. It is our recommendation that an update

of the Aquatic Park Master Plan be completed to re-address the goals as well as

provide updated recommendations for the location of the suggested elements and

possible new program elements for the total 90 acres of Aquatic Park.

 

Chapter 3 – Relationships to Other Plans

PENNONI ASSOCIATES INC.

Consulting Engineers

 

24

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

25

 

Chapter 4 – Recreation Standards and

Needs Assessment

 

INTRODUCTION

 

There are a variety of methods and approaches that have been used in the past by

different agencies to consider the necessary and appropriate amount and type of

parkland for a given region. The Master Plan presents two different methods for

determining the need for recreational open space, which may be applied to

Pequannock Township.

The methods include 1) an analysis based on New Jersey’s Balanced Land Use

Guidelines and 2) a population –based analysis

The population-based standards set a goal for a finite period of time, which may best

be used for short-term goals. The Land Use standards set their goals in perpetuity,

recognizing that land is finite and any preservation efforts now will benefit all

generations to follow.

It is important to note that the population based analysis does not relate the standards

to the natural resources of the area such as wetlands, stream corridor, wooded areas

and wildlife habitats.

The second analysis looks at recreation activities and the facilities required to provide

these activities. This Master Plan establishes the type and quantity of facilities the

Township should develop in the future. The ultimate goal of this analysis is to

quantify the amount of public open space required to meet the Township’s

recreational needs.

 

BALANCED LAND USE GUIDELINES

 

New Jersey’s State Comprehensive Outdoor and Recreation Plan identifies the goal for

New Jersey municipalities to provide three percent (3%) of the total developable lands

within the municipality for recreation uses. This balanced land use approach takes

into consideration the extent of wetlands and steep slopes in the municipality and

removes those lands from the total developable lands within the municipality.

According to this methodology Pequannock Township, with its 647 acres of park land,

has preserved fourteen percent (14%) of its overall lands and thirty percent (30%) of

the Township’s developable lands for recreation purposes.

This analysis is unevenly balanced, however, due to eighty-two percent (82%) of the

preserved lands suitable only for passive recreation or resource areas due to wetlands

and steep slopes on the site. So while there is a significant amount of lands preserved

 

Chapter 4 – Recreation Standards and Needs Assessment

PENNONI ASSOCIATES INC.

Consulting Engineers

 

26

for recreation purposes the Township does not have a balance between lands suitable

for active and passive recreation.

 

POPULATION-BASED RECREATIONAL OPEN SPACE NEEDS

 

ASSESSMENT

 

In 1995, the National Recreation and Park Association (NRPA), in collaboration with

the American Academy for Park and Recreation Administration, published “Park,

recreation, Open Space and Greenway Guidelines.” The revised guidelines

acknowledge that each community is unique, and that it is difficult to apply one set of

special standards to all communities as had been done in the past. Instead, the

guidelines reflect a more systematic planning approach that takes into account the

unique needs, desires and resources of communities as well as changing

environmental, social, economic and demographic trends.

With this framework in mind, the NRPA takes a different approach to park planning,

analyzing the types of parks and facilities require for each individual community, along

with the amount of acreage required to site those kinds of parks and facilities. The

process includes identifying the classifications of parks and the level of service for

each facility within each park classification. Map 2 shows the park and school

locations within Pequannock Township. The guidelines currently being discussed take

into consideration the common shared use of school facilities with Township

recreation programming needs.

 

Park Classifications

 

Mini Park

 

These parks are located within walking distance of the area serviced, and they address

limited or isolated recreational needs. These parks are the vest pocket and tot lots of

the past. Their small size requires intense development and little to no buffer

between the park and adjacent land users is provided. Map 3 identifies the locations

of the Mini Parks within Pequannock Township.

The standards for mini park development are as follows:

Service Area: Ľ mile radius to serve walk-in recreation needs of surrounding

populations.

Acreage/Population Ratio: 0.5 acres per 1,000 persons

Desirable Size: 2500 s.f. to 1 acre

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

27

Potential Facilities:

 

Playground

 

˝ Basketball courts open play area

 

Picnic tables with grills (no shelter)

 

Benches or bench swings

 

Landscaped public use area

 

Scenic overlook

 

Neighborhood Park

 

Neighborhood parks are the basic unit of the park system and serve as the recreational

and social focus of the neighborhood. The parks are usually located within walking

distance of the area serviced, and they provide a variety of activities of interest to all

age groups. Creating a sense of place by bringing together the unique character of the

site with that of the neighborhood is vital to successful design. While their small size

requires intense development, fifty percent of each site should remain undisturbed to

serve as a buffer between the park and adjacent land users. Map 4 identifies the

locations of the Neighborhood Parks within Pequannock Township.

The standards for neighborhood park development are as follows:

Service Area: ˝ to 1 mile distance uninterrupted by physical barriers.

Acreage/Population Ratio: 2 acres per 1,000 persons

Desirable Size: 5 to 10 acres

Potential Facilities:

 

Playground

 

Court games

 

Informal play field

 

Volleyball

 

Trails/walkways

 

Picnic shelters with grill

 

Picnic tables with grills (no shelter)

 

Benches or bench swings

 

50% of site to remain undeveloped

 

Parking (7-10 spaces)

 

School-Park

 

The trend in public agencies is toward joint use. Through joint use the patrons of both

schools and parks benefit for shared use of facilities and valuable land resources.

School-park sites often complement other community open lands, such as Hillview

Elementary School and Hillview Park in the Township. The school park concept

maximizes the joint use concept and provides a planned facility which maximizes

public funds. The school park concept typically varies depending on the school. The

elementary/middle school provides the ideal setting for a neighborhood park. While

 

Chapter 4 – Recreation Standards and Needs Assessment

PENNONI ASSOCIATES INC.

Consulting Engineers

 

28

the middle/high school follows the function of a community park or youth sports

complex. Map 5 identifies the locations of the School-Parks within Pequannock

Township.

The standards for neighborhood park development are as follows:

Service Area: Varies depending on school type and park type.

Desirable Size: Varies depending on school type and park type.

Potential Facilities: Varies depending on school type and park type.

 

Community Park

 

Community parks provide for the recreation needs of several neighborhoods or large

sections of the community. A range of facilities is typically provided and may support

tournament competition for athletic and league sport or passive recreation. These

parks also present opportunities of nontraditional types of recreation. Fifty percent of

the community park site should be developed for only passive recreation; these

relatively undisturbed areas may serve as buffers around the park and/or act as

buffers between active facilities.

Community parks sites should have varying topography and vegetative communities.

Forested areas should have a variety of tree species. Cleared areas should be present

for siting active recreational facilities. One or more natural water feature(s) such as a

lake, river, or creek is desirable in community parks. Parkland should also be

contiguous and strategically located in order to be accessible to all users within the

neighborhoods it serves. Map 6 identifies the locations of the Community Parks within

Pequannock Township.

The standards for neighborhood park development are as follows:

Service Area: ˝ to 2 mile radius.

Acreage/Population Ratio: 2.5 acres per 1,000 persons

Desirable Size: 30 to 50 acres

Potential Facilities:

 

Recreation center

 

Basketball courts

 

Tennis courts (lighted)

 

Baseball/softball fields

 

Multi-purpose fields

 

Soccer fields (lighted)

 

Swimming pool

 

Amphitheater

 

Observation decks

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

29

 

Picnic shelter

 

Picnic shelters with grills

 

Picnic table with grills

 

Benches or bench swings

 

Nature trails

 

Restroom/concessions

 

Parking Playgrounds

 

Volleyball courts

 

Disc golf

 

Lakes

 

Paddle boat/canoe rental

 

Fishing piers/boat docks

 

50% of site to remain undeveloped

 

Specialty facilities may be added to, or substituted for, other facilities

depending on community needs or special site characteristics.

 

Sports Complex

 

Sports complexes function as the major source of active recreation in the community.

They are typically at larger and fewer sites strategically located throughout the

community. Sports complexes should be developed to accommodate the specific

needs of user groups and athletic associations based on demands and program

offerings. Passive recreation opportunities are usually limited, but may be found in

the undisturbed areas, such as within surrounding buffers.

Sites for sports complexes should be relatively flat to alleviate excessive grading of

active facilities. Since most of the land will be developed for athletic fields, sites

without significant vegetation or natural features are acceptable and in some cases

preferable. Sites should be accessible from major thoroughfares. Direct access to

residential areas should be limited and buffers, where adjacent to residential area,

should be provided. Map 7 identifies the locations of the Sports Complex within

Pequannock Township.

The standards for neighborhood park development are as follows:

Service Area: ˝ to 3 mile radius.

Acreage/Population Ratio: 5 acres per 1,000 persons

Desirable Size: 25 to 80 acres

Potential Facilities:

 

Ball fields

 

Soccer fields

 

Football fields

 

Outdoor and indoor skating rinks

 

Tennis courts

 

Chapter 4 – Recreation Standards and Needs Assessment

PENNONI ASSOCIATES INC.

Consulting Engineers

 

30

 

Playground

 

Hard courts

 

Volleyball courts

 

Group picnic area with shelter

 

Parking

Support Facilities:

 

Recreation center

 

Tennis center

 

Running track

 

Amphitheater

 

Restrooms

 

Special Use Park

 

The Special use park classification covers a broad range of parks and recreation

facilities oriented toward a single-purpose use. These parks should be viewed as

strategically located community-wide facilities rather than as serving a well-defined

neighborhood or areas. The site should be easily accessible from local and major

roads and centrally located if feasible. The Special Use Parks within Pequannock

Township are Pequannock Valley Park and Woodland Lake.

The standards for neighborhood park development are as follows:

Service Area: Community-wide

Desirable Size: Varies depending on use.

Potential Facilities:

 

Community centers

 

Tennis center

 

Performing arts facilities

 

Public buildings

 

Ornamental gardens

 

Hockey arena

 

Natural Resource Area

 

Natural resource areas are lands set aside for preservation of significant natural

resources, remnant landscapes, open space and visual aesthetics/buffering. These

sites consist of individual sites with natural resources and lands that are unsuitable for

development but offer natural resource potential.

Recreational opportunities include nature viewing and study. Natural resource areas

can also function as greenways. All development should be kept to a level that

preserves the integrity of the resource.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

31

Size and location of the Natural Resource Area will be dependent upon the availability

and opportunity and quality of the site for preservation. Map 8 identifies the locations

of the Natural Resource Area within Pequannock Township.

Examples:

 

Parcels with steep slopes and natural vegetation

 

Drainage ways and ravines

 

Surface water management areas

 

Utility easements

 

Wetlands/lowlands

 

Shorelines along waterways, lakes, and ponds

 

Greenways

 

Greenways tie the park system components together to form a cohesive park

environment, they emphasize harmony with the natural environment, allow for

uninterrupted and safe pedestrian movement between parks and other open space

components throughout the community, provide people with a resource based outdoor

recreational opportunity and they can enhance property values.

Greenways can either be “natural” following natural resources or “man-made” built as

part of a development project or during renovation of old development areas such as

an old railroad bed. Existing and proposed greenways are noted in the Township

Master Plan

Desirable Size: 50 to 200 foot width

Potential Activities:

 

Hiking

 

Walking

 

Jogging

 

Bicycling

 

In-line skating

 

Cross-country skiing

 

Horseback riding

 

Canoeing

 

Chapter 4 – Recreation Standards and Needs Assessment

PENNONI ASSOCIATES INC.

Consulting Engineers

 

32

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township

Recreation Master Plan

 

Natural Resource Areas

 

Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

BERGEN

PASSAIC

ESSEX

HUDSON

MORRIS

SUSSEX

 

HUDSON HUDSON

 

I-80

I-280

I-287

I-95

GARDEN STATE PARKWAY

NEW JERSEY TURNPIKE

 

I-78

 

I-287

 

Legend

 

Park Boundaries

Major Roads

 

Natural Resource Areas

 

Aquatic Park NRA

Hidden Cove NRA

Meyers Brook NRA

Mountainside Park NRA

Pequannock Township

 

45

 

Map 8

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Recreation Need by Park Classification

 

Level of Service guidelines are set for park classifications except School-Park,

Greenways and Special Use Parks.

Based upon the 2005 census data all of the park classifications that receive a level of

service in Pequannock Township have a deficit to what should be provided. There is a

deficit of eight (8) acres of Mini-Parks, a deficit of eight (8) acres of Neighborhood

Parks, a deficit of sixteen (16) acres of Community Parks and a deficit of fifty-seven

(57) acres of Sports Complex.

 

Table 2 ~ Parks by classification, standards and deficiencies / surplus

 

The majority of the Township parks are located in the central to southern area of the

Township. This is most likely due to the location of wetlands and floodplain

influencing the initial settlement of the Township with the first homesteads in the

north central section of town. When parks and recreation development came to the

forefront there was more opportunity to set aside lands for recreation and leisure in

the central and southern part of town. This provides an imbalance to access to the

provided parks and their recreation and leisure facilities. The residents in the

southern and south-central part of the Township have better access to facilities than

those in the north and north-central part of the Township.

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

47

 

Chapter 4 – Recreation Standards and Needs Assessment

PENNONI ASSOCIATES INC.

Consulting Engineers

 

48

Two Mini Parks, Lyon and Riverside Parks, and one Neighborhood Park, Lyman Park,

are located in the southeastern corner of the Township. One neighborhood park,

Foothills Park, is located in the northwest corner of the Township. Pequannock

Township has one Community Park, Greenview Park, in the southwestern corner of the

Township. There are two Sport Complexes, Town Hall Field and Washington Park,

centrally located. Hillview Park is considered part of a School-Park as it is adjacent

to Hillview Elementary School and Pequannock Valley Middle School. North Boulevard

and Stephen J. Grace Elementary Schools and Pequannock Township High School are

other School-Parks within the Township (see Map 2 for park and school locations).

While the schools are not managed directly by the Township they are a valuable

resource that should continue to be actively pursued for partnership for recreation

use.

There are four natural resource areas within Pequannock Township, Aquatic Park,

Hidden Cove, Meyers Brook and Mountainside Park. Wetlands can be found on ninety

seven percent (97%) of the land within Aquatic Park, seventy one percent (71%) of

Hidden Cove lands and thirty seven percent (37%) of Meyers Brook’s lands. Steep

slopes of thirty percent (30%) or more comprise ninety percent (90%) of the land

within Mountainside Park. The sensitive lands associated with these parks and the

respective regulations as well as their location and configuration (Meyers Brook) limit

the development opportunities for these parks to passive trail development.

Community parks can provide facilities similar to Neighborhood Parks and Mini Parks.

Neighborhood Parks can also provide facilities similar to Mini Parks.

When evaluating the deficit of park classifications and the typical uses within those

park classes the park classification hierarchy is taken into consideration. For example,

the facilities found in a Mini Park may also be found in all of the other park

classifications except Natural Resource Area and Greenways. This could mean that a

Neighborhood Park can supply the demand for a Mini Park depending upon the location

within the Township.

In addition, School Complexes may also partially supply the demand for certain park

classifications based upon the available facilities and availability for use. In

Pequannock, Stephen J. Grace and Hillview Elementary Schools have playgrounds.

They may act as Mini Parks, Neighborhood Parks or Sports Complexes during non-school

hours.

 

Mini Parks

 

Mini Parks and the typical facilities of such parks are well distributed in the southern

section of town. In addition to Lyon Park and Riverside Park, Greenview Park and

Stephen J. Grace Elementary School are in the southern section of town. These

provide the facilities that a Mini Park would and are well distributed in the southern

section of town.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

49

Hillview Elementary School serves as a Mini Park in the center of town. There is a gap

in service for the residents to the south and west of the school.

Two sites in the northern section of the Township provide the facilities found in a Mini

park, North Boulevard School and Foothills Park. Both sites have a playground.

Access to Foothills Park, however, is by vehicle not by foot as there is no safe

pedestrian access to the park. There is a gap in service between Hillview and North

Boulevard Schools north and south and east to west in the Township.

 

Neighborhood Parks

 

The Neighborhood Parks are located at opposite ends of the Township (northwest and

southeast). Greenview Park, a Community Park, can serve the need as a Neighborhood

Park. There is a gap in service with no Neighborhood Park in the central or the

northeast section of town.

 

Community Park

 

Greenview Park is the only Community Park within the Township. This serves the

residents in the southwest corner of town with a gap in service for the remainder of

the Township.

 

Sports Complex

 

Sports Complex should be strategically located within the Township. The current

facilities are centrally located on the eastern side of town.

 

School Complex

 

The schools in Pequannock Township are located in the north-south central corridor.

They serve as Mini Parks, Neighborhood Parks, and Sports Complexes. As these lands

are not managed by Pequannock Township they were not included within the

surplus/deficit calculations but will be considered as part of the facility

recommendations.

 

DEMOGRAPHIC ANALYSIS

 

We must remember as we go through the planning process for the Township-wide

Recreation Master Plan that we are planning for people. Since the level and quantity

of parks and recreation services demand is directly related to the number of people

demanding the given services, changes in both the number and composition of that

local population affects local government planning. A youthful population makes

different demands on parks facilities than a much older population does, and an

increase in certain cultural groups – Hispanics, for example- can create yet another set

of demands.

Since estimates of population change are crucial to planning, budgeting and financing

park improvements, they are essential to this Master Plan.

 

Chapter 4 – Recreation Standards and Needs Assessment

PENNONI ASSOCIATES INC.

Consulting Engineers

 

50

 

Population

 

The population in Pequannock Township was in decline in the later portion of the 20th

 

century (Table 3). According to the Pequannock Township Master Plan (1995) the

decline was in large part due to the decrease in household size and a relatively stable

housing stock. The population in the beginning of the 21st Century is on a slight

increase and the population trend will continue to increase with a projected increase

in 2005 of 12.13% according to projections from the American Community Survey.

 

1970 1980 1990 2000 2005

 

Population total 14,396 13,776 12,884 13,888 15,586

 

% change -4.31% -6.48% 7.79% 12.23%

 

Table 3 ~ Pequannock Township Population Trends

 

The age of Pequannock Township residents has been shifting over the last forty years

Table 4). There was a big drop in the residents under 5 years of age (-41.10%)

between 1970 and 1980. The total numbers of that segment of the population has

been gradually increasing since then and represents the second greatest change in age

cohort in the Township from 1990 (21.72%). There has been a steady decline in the

residents 5 – 24 years of age from the 1970 through 2000, although in the last 10 years

the decline is relatively insignificant (0.52%). The change in total numbers in the 25-

44 age cohort has shown slight fluxuations from 1970 to 2000. Similarly the numbers

of resident’s aged 45-64 have shown a steady increase over the years since 1970. The

age group that has show the greatest growth in Pequannock Township is those

residents aged 65 and over. This age group has significantly increased since 1970

with the latest increase of 25.38% from 1990, the largest increase from 1990 in any

age cohort.

 

1970/1980 1980/1990 1990/2000

Age Cohort

Change in

Total Change

Change in

Total Change

Change in

Total Change

 

Under 5 -484 -41.10% 93 13.40% 169 21.72%

5 - 24 -675 -11.90% -1543 -31.00% -18 0.52%

25 - 44 -137 -3.60% 223 6.10% 199 5.08%

45 - 64 406 13.90% 128 3.80% 298 9.55%

65 and over 316 38.60% 424 37.40% 396 25.38%

 

Table 4 ~ Pequannock Township Age Cohort Trends

 

The percent of the total population for each age cohort follows the individual trends

for the change in the total for each age cohort (Table 5). While the greatest changes

in total numbers have been occurring in the under 5 and 65 and over age cohorts they

still comprise the two smallest age groups in Pequannock Township in 2000. Their

increasing trends, however, indicate the need to pay special attention to confirm

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

51

there are adequate facilities for an increasing population in these two age groups.

The age group comprising the greatest segment of the population in 2000 is the 25-44

age cohort. This percent of the total population for this age group has shown slight

fluxuations since 1970. The age group showing the greatest change in the overall

percentages of the total population is the 5 – 24 age cohort, decreasing by almost 15%

since 1970 when it had the greatest portion of the population (39.40%). The last age

cohort is 45-64 which has remained constant over the last thirty years at just over 24%

of the total population.

 

Percent of Total Population

Age Cohort 1970 1980 1990 2000

Under 5 8.18% 5.02% 6.06% 6.82%

5 - 24 39.40% 35.99% 26.99% 24.83%

25 - 44 26.44% 26.44% 30.50% 29.64%

45 - 64 20.29% 24.35% 24.30% 24.63%

65 and over 5.69% 8.20% 12.15% 14.08%

 

Table 5 ~ Pequannock Township Age Cohort Trends as a Percent of the Total Population

 

Population density

 

There are two areas of concern when studying population. The first is the actual

number of people dwelling within the area. The second is the density of this

population, or how closely the actual number of people approaches the number of

planned for during the zoning process. Combined, the two provide important

indicators of the need for the size and location of park and recreational programs and

facilities.

Density figures provide a measure of an area’s degree of development and land

availability. Park and Recreation’s land use view differs somewhat from that of other

Township department: it must look into the future well in advance of build-out to

identify suitable land for acquisition and park development. By the time an area has

reached 50% density, most of the choice recreation lands may well have been taken

for other purposes.

The total acres in Pequannock Township are 4565. In 2000 the population was 13,888

which produces an overall population density of 3.04 persons per acre. The areas of

greatest density generally runs north south between the Newark-Pompton Turnpike

and Boulevard and State Rt. 23 and the southern Pequannock Township Boundary (Map

9). The population continues from Boulevard to the west getting gradually less dense

the further away from Boulevard. The one exception is a residential condominium

development called “The Glen” that lies to the northwest of Sunset Road.

 

Housing

 

Chapter 4 – Recreation Standards and Needs Assessment

PENNONI ASSOCIATES INC.

Consulting Engineers

 

52

Pequannock’s 13,888 residents live in 5,026 housing units. The average household size

is 2.76 people and the average family size is 3.23 people. Of the 5,026 housing units

89.5% (4,497) are owner-occupied and 10.5% (529) are renter-occupied. This

represents a change from the 1999 Census reports with slight increase (1.40%) in

owner-occupied and a slight decrease (10.26%) in renter occupied.

The average household size of a rental occupied unit is 1.88 persons and of an owneroccupied

unit is 2.86 persons. This is a continued decline from the 1990 Census of 2.1

persons and 3.1 persons per rental and owner-occupied housing unit respectively.

 

Education

 

Education has been shown to have a high correlation with leisure activity. The higher

the educational attainment, the more activities participated in and the more frequent

the participation. According to the 2000 Census Pequannock Township out of 9,495

residents 25 years of age and older 93.0% earned a high school diploma (including

equivalency), which is comparable to overall Morris County at 90.6% and higher than

overall New Jersey State t 82.1%

In addition out of Pequannock Township residents 25 years of age and older 19.1% had

some college but no degree, 5.8% earned an Associate degree and 37.5% earned a

Bachelors degree or higher. The percentage of Morris County residents 25 years of age

and older earning a Bachelors degree or higher as noted in the 2000 Census is 44.1%

and for New Jersey as a whole is 29.8%.

 

Income

 

Income is also tied to recreation participation, the higher the income, the more active

people are in recreational pursuits. In part, income also represents the ability to pay

for recreation activities and to travel to recreation areas.

The 2000 Census evaluates income for households and families. A household is defined

as a group of unrelated people living together. A family is defined as a group of

people related in bloodline living together. According to the 2000 Census the median

household income in Pequannock Township is $72,729. This is 24% higher than the

State household median income of $55,146 and 6% lower than the Morris County

median household income of $77,340. The Pequannock Township median family

income is $84,487. This is 22% higher than the State median family income of $65,370

and 6% lower than Morris County median family income of $89,773.

In 1999, according to the 2000 Census, 534 persons or 3.8% of all people for whom

poverty status was determined, were below the poverty level in the Township. This is

an increase from the 1.366% reported in the 1989 Census (Morris County Master Plan,

1995). According to the 2000 Census 2.5% (96) of the families in Pequannock Township

are below the poverty level, 8.0% (24) of the families with a single mother

householder are below the poverty level and 3.0% (414) of individuals are below the

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

53

poverty level. These percentages are similar to Morris County poverty percentages of

2.4%, 10.0% and 3.9% respectively. The Pequannock Township poverty percentages are

significantly lower than the State’s poverty percentages of 6.3%, 19.4% and 8.5%

respectively.

 

FACILITY NEED

 

This Master Plan evaluates the facility demand based upon previous information

discussed in this report, input from the Parks and Recreation Director, the Recreation

Advisory Board and stakeholders. This information as well as analyzing the

geographical location of the facilities was used in developing the facility needs.

Pequannock Township provides a variety of indoor and outdoor recreation and leisure

opportunities for residents. There is a need for additional facilities to support the

demand for these programs.

The outdoor facilities provided include boating, camping, fishing, hiking and nature

trails, picnic areas, ice skating, playgrounds, swimming and athletic fields. The

Township also has a Senior Center. The Township has a need to provide 3-4 additional

soccer/lacrosse fields and one baseball field to meet the growing demand. The other

outdoor activities are adequate in number. There are opportunities to capitalize on

the undeveloped lands to augment these facilities. This, however, is not a priority.

The Township does not have any facilities to support other indoor programs such as

basketball, volleyball, jazzercise, aerobics, little crafters, hands on fun, children’s

ceramics, karate, etc. The Parks and Recreation Department relies on Board of

Education (BOE) facilities for these programs. Time and space for these programs in

BOE facilities is getting less and less over the years as the BOE before school and after

school programming is expanding. The Township needs an indoor facility to continue

to be able to provide the level of programming and services the residents are

accustomed to and the Township has the ability to provide with available facilities.

The Recommendations section of this report lists specific action items to address the

identified needs.

 

Chapter 4 – Recreation Standards and Needs Assessment

PENNONI ASSOCIATES INC.

Consulting Engineers

 

54

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Foothills Park

Rockledge Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

Population Density (2000)

 

Legend

 

Pequannock Township

Park Boundaries

Roads

Lakes

Streams

 

Population Per Square Mile

 

0 - 2000

2001 - 5000

5001 - 7000

7001 - 9000

> 9001

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 9

 

55

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Chapter 5 – Inventory and Analysis of

Existing Resources

 

PROCESS

 

Existing information was gathered from several sources; GIS Data from New Jersey

Department of Environmental Protection and New Jersey Geological Society, existing

maps and documents, site visits and staff interviews and discussions.

 

GIS Mapping

 

Geographic Information System data was gathered for the following: land use, land

cover, wetlands, surficial and bedrock geology, depth to bedrock, depth to

groundwater, aquifers and sole source aquifers, census data, groundwater recharge

 

Site Visits

 

Between June and November of 2006 site visits were conducted for each of the parks

within Pequannock Township to evaluate the existing conditions including quantity and

quality of recreation opportunities provided.

 

PEQUANNOCK TOWNSHIP PARK LANDS

 

The location of Pequannock Township at the

base of the Waghah Mountains and at the

confluence of three rivers gives the

Township a unique opportunity to provide a

wide variety of recreation and leisure

opportunities. Pequannock Township has

fourteen parks totaling 646.6 acres with

sizes ranging from 0.1 acre in Lyon Park to

310 acres in Mountainside Park. The green

highlighted areas in Figure 3 illustrate the

recreation facilities provided by Pequannock

Township. The red highlighted areas on the

same figure are the Township Board of

Education facilities. (See also Map 2 for a

larger scale map identifying each park by

name.) Table 2 on the next page identifies

the size of each park and the amenities

within. This table also identifies those

outdoor facilities owned by the Pequannock

Board of Education whose facilities are used

by the Park and Recreation Department.

 

Figure 3 ~ Township Park and Board of

Education facility locations.

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

57

 

Chapter 5 - Inventory and Analysis of Existing Resources

 

Table 6 ~ Facility Amenities Matrix

 

PENNONI ASSOCIATES INC.

Consulting Engineers

 

58

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Aquatic Park

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

59

 

Figure 4 ~ Meadow area in

Aquatic Park utilized as a

circular track by ATVs.

Figure rea in

Aquatic Park.

5 ~ Forested a Figure 6 ~ Waterway in

Aquatic Park.

 

and

s.

on the

ails.

is

f

he park due to the

length of trail that would have to be hiked to reach this area.

e

squehanna Western Railway on the west.

rested

The seventy-seven (77) acres of Aquatic

Park provides the opportunity for varied

unique recreation opportunities. These

could include a blueway with canoe portage

points, flora and fauna observation,

demonstration gardens, nature trails,

guided hikes and environmental program

The existing park, however, provides

limited hiking opportunities, whose trails

appear to be utilized heavily by ATVs. As

the majority of the park is classified as

wetlands, the ATVs are disrupting the

environmental ecosystem as well as making it dangerous for people to hike

tr

There is no easy access to the park as the only parking available is north of the park

and patrons must hike to the park prior to beginning their enjoyment of the park. Th

limits the number of people utilizing the facility and increases the possibility of ATV

use with little policing of the ATV activity occurring. It also limits the possibility o

the larger number of patrons accessing the southern limits of t

 

Cherry Street Park

 

Cherry Street Park (14-acres) fronts Jefferson Street to

the north, residential to the east and south and th

New York Su

Sixty-nine percent (69%) of site is classified as fo

wetlands with the area fronting New Street nonwetlands.

The City of Newark water supply pipeline

right-of-way (ROW) cuts across the northeast corner of

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

60

 

Figure 7 ~ Open play area in

Foothills Park. I-287 and

Mountainside Park are in the

background.

Figure 8 ~ Sledding at

Foothills Park.

Figu at

Foothills Park.

 

oted ROW,

owever, can be utilized for this purpose.

 

oothills Park

 

hip and

es

ea

ke it

ated at the foot of the I-287

mbankment restricts access to the pond from the east.

It is

f

rk

from

the park. There is no designated access point into this park. The n

h

 

F

 

Foothills Park (27-acres) is located in the

northwestern portion of the Towns

abuts I-287. It is separated from

Mountainside Park by I-287. The park

provides a playground and opportuniti

for open play in the field from spring

through fall and sledding in the winter.

There is a man-made pond about fifteen

feet below the parking grade. The only

access to the lake is from the parking ar

across a lawn down a desire path to the

pond edge. The existing grades along

West Parkway at about twenty to twenty-five feet above the pond grade ma

difficult to access. In addition, a police training range loc

e

 

re 9 ~ Playground

 

Greenview Park

 

Greenview Park (31-acres) is

located in the south-western

portion of the Township.

surrounded by residential

development on the north,

east and south and Lincoln

Park Airport on the east side o

Beaver Brook Road. The pa

does not have access

Beaver Brook Road.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

61

 

Figure 12 ~ Greenview Park

tennis courts and attendant

station.

Figur ark

playground area.

e 13 ~ Greenview P Figu ark

restroom facility.

 

and

nd in

League fields, tennis courts,

strooms and parking.

n. Some

ass

estrooms are functional, however, should be updated.

e with swimming. As such, no boating will be able to be

g agreement to allow limited parking for residents who want to

ccess Hidden Cove.

This park is one of the larger parks in the Township

provides a variety of passive and active recreation

amenities. The following amenities can be fou

Greenview Park: handball courts, ice skating,

lacrosse/soccer fields, picnic area, playground, pond,

sledding, softball/Little

 

Fig

 

re

In general the amenities are in good conditio

amenities require maintenance and general

improvements to address high use and site drainage

issues. The softball field is in overall good condition

requiring annual maintenance on the infield and gr

areas. The soccer / lacrosse fields are in need of

regrading, seeding/sodding and irrigation to begin to

address the high use of the fields. The playground

area drainage needs to be addressed as it appears

water drains through the playground area. It also

appears the decomposition of the safety surface is

accelerating possibly due to this as well as ground

water. The tennis courts are in good condition. The

 

ure 10 ~ Greenview Park

soccer/lacrosse field.

Figure 11 ~ Greenview Park

Softball/Little League field.

 

r

 

re 14 ~ Greenview P

 

Hidden Cove

 

Hidden Cove (20-acres) is located at Lincoln park Road and

Boulevard. It consists of a portion of a lake and wooded area a

portion of which has wetlands. This facility is used for fishing and

hiking. The lake is connected to Lincoln Park’s swimming facility.

As such, the uses on Pequannock Township’s side will have to remain

compatibl

allowed.

There is poor access with no on-site parking and poor parking

availability on adjacent roadways. The adjacent land owner is not

open to a shared parkin

a

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

62

 

Hillview Fields

 

Figure 15 ~ Hillview Field

softball/little league field.

 

y

,

is

s

the fields located to the

me to “rest” and regenerate. The

fields and fencing are in fair condition. The parking lot is in good condition.

arcels located in

ntral of the park area.

l

he

a

e has poor

drainage and takes several days to dry out after a normal rain event.

Hillview Fields (11-acres) is located in the south-central

portion of the Township. It is contiguous with Hillview

Elementary School to the west and Pequannock Valley

Middle School to the north. Located on the propert

are three softball/little league fields, a baseball field

parking and the Township library. The parking lot

shared with Hillview Elemen

Elementary School also ha

a playground that is near

tary school. Hillview

north of the school building.

The fields are in fair to poor condition. They receive

heavy use from both softball/baseball and

soccer/lacrosse teams. The grass is in poor condition

from overuse and no ti

in

 

Lyman Park

 

Lyman Park is twenty (20) acres of undeveloped

park land in the southeast corner of the Township.

It is surrounded by residential development. In

addition there are residential our-p

the north ce

The park is primarily forested with a small centra

clearing. Access is from Hampton Avenue off of

Roosevelt Street. Fifty-one percent (51%) of the

lands are wetlands. Those that are not include t

central clearing and residences and the eastern

portion of the site. Existing amenities include

playground, open play area and parking along the cul-de-sac. The sit

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Figure 18 ~ Residential outparcels

in Lyman Park.

Figure 17 ~ Hampton Avenue

access.

Figure 16 ~ Lyman Park

clearing and playground in

trees.

 

Lyon Park

 

Lyon Park is a mini park located on a single lot on Hilton

Street at E. Franklin Street. The amenities include

playground equipment and benches. They are in good

condition.

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

63

 

Figure 19 ~ Lyon Park

ayground equipment.

 

d

 

pl

 

Meyers Brook

 

Meyers Brook is a narrow band of twenty-six (26) acres of

land that follows a tributary of the Pompton River locally

called Meyers Brook. It is located in between backyards

in the residential east-central portion of the Township.

It connects with Pequannock Valley Park and Woodlan

Lake. There are no recreation amenities in this park.

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

64

 

Mountainside Park

 

Mountainside Park is located in the northwest corner of the

Township. It is cut off from the remainder of the

Township by I-280. Access to the park is from Mountain

Avenue Drive. Mountainside Park consists of three hundred

and ten (310) wooded acres, hiking trails, camping area,

views of the Pequannock Valley and a small parking area.

The trails are varied in the section north of the parking lot

and east of the utility easement. These trails are blazed

but some are overgrown and unclear. There were no

apparent trails to the south of the parking lot or west of

the utility easement. Students travel to the park to study

the geological formations found there.

 

Figure 20 ~ View from

Mountainside Park

Figure 21 ~ Trail and marking

at Mountainside Park.

Figure 22 ~ Mountainside Park

camp area

 

Pequannock Valley Park

 

Pequannock Valley Park is the Township’s only

to be

ls,

a portion of

d

swimming facility. There is a membership fee

able to utilize the twenty-seven (27) acre facility.

Recreation amenities include a pond with a sand

beach, playground area, picnic areas, nature trai

basketball court and parking.

The lake was created by damming

Woodland Lake. The dam is required in order to

regulate the water quality. This dam has receive

repairs recently and is in need of additional repairs, in the amount of approximately

$250,000, within the next five years. The remaining amenities are in good condition

but have not been updated.

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

more

nt may

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

65

 

Figure 23 ~ Pequannock Valley

k swimming lanes.

Figu

Pe

re 24 ~ Members entering

quannock Valley Park.

Figure 25 ~ Pequannock Valley

Park picnic area with lake in

the background.

Par

 

Riverside Park

 

Riverside Park (2 acres) is located adjacent

to the Pompton River in the southeast corner

of the township. This wooded site has views

of the river and Wayne Township. There is

also a piece of playground equipment and

benches.

 

Rockledge Park

 

Rockledge Park (21-acres) is located on Sunset

Road with access also from Farm Road and Coopers

Court. The majority of the site is forested with

the area off of Coopers Court an open grass area.

Sixty seven percent (67%) of the site is classified as

wetlands with the eastern finger extending

towards Sunset Road not classified as forested

wetlands. These same areas are New Jersey

Landscape Project Rank 3 for the wood turtle.

The wood turtle is a state threatened species.

Rank 3 indicates that there have been one or

occurrences of sighting the species. The

possibility of the wood turtle on site will require further studies to be completed prior

to any site development. Based upon the study findings the site’s developme

be restricted.

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

66

 

Town Hall Field

 

Town Hall field is located on Township property

behind Town Hall off of the Newark Pompton

Turnpike. Recreation amenities on this site include

baseball field, two basketball courts, a gazebo, picni

table, the Senior Building and parking. Also on th

site include the Township Police Headquarters and

First Aid Squad.

a

c

e

the

The baseball field is in good condition. The grass has

irrigation and has helped the playability of the field.

The infield is oversized. The basketball courts need resurfacing. This is scheduled as

a 2007 capital improvement. Cars park on the current courts during the winter time.

 

Figure 26 ~ Town Hall baseball

field.

Figure 27 ~ Town Hall

basketball courts.

 

Washington Park

 

Washington Park is located off of Jefferson Street across from Cherry Street Park.

Access to the park is also from Adams Street to the eastern parking lot and Washington

Street to the western parking lot.

The fourteen (14) acres of Washington Park are an athletic complex with three

softball/little league fields, scoreboard buildings, concession building and parking. All

three fields have sports lighting and irrigation. The ball

fields are all in good condition. The eastern parking lot is

in good condition. The western parking lot has several

large puddles after a normal rain. The paving is also in

need of replacement.

Other uses within the park include the Pequannock

Township Department of Public Works (DPW)and Animal

Control. DPW is using almost half of the park as a

construction debris dumping yard and for material and

equipment storage. This area is the first thing seen as you

 

Figure 28 ~ Washington Park

southern ball field.

l

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

enter the park from the main entrance off Jefferson Street. Construction traffic uses

this entrance to access the DPW yard. This has damaged the entrance road and

parking area. The animal control building is on the northern boundary of the park.

 

Figure 30 ~ Washington Park

concessions building.

Figure 31 ~ Washington Park

northern ball field.

Figure 29 ~ DPW dumping area

in Washington Park.

 

Woodland Lake

 

The majority of the forty (40) acres of the Woodland Lake

property is the lake itself. The lake is accessed off of

Alexander Avenue into a gravel parking area. The lake is

used for fishing and boating. There is a desire path along

the southern lake edge that connects to what appears is

access from the Rt. 23 interchange to a property north of

Woodland Lake. Woodland Lake is contiguous with

Pequannock Valley Park and Meyers Brook.

The gravel entrance drive and parking area are in fair condition. The boat launch and

the eastern lake edge are in poor condition. Other amenities include benches and

views.

 

Figure 32 ~ Woodland Lake

boat launch and gravel

parking area.

Figure 33 ~ Trail around Figure 34 ~ Woodland Lake

Woodland Lake

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

67

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

68

 

PEQUANNOCK TOWNSHIP BOARD OF EDUCATION LANDS

 

Pequannock Board of Education (BOE) has three elementary schools, one middle school

and one high school that is manages for the residents of Pequannock. The athletic

fields at all of the elementary schools and the middle school are used also for

Township Park and Recreation Department programs. These schools are also utilized

for the indoor programming.

 

OTHER RECREATION OPPORTUNITIES

 

Morris County operates the 18-hole Sunset Valley Golf Course located adjacent to I-287

off of West Sunset Road. This course, designed by Hal C. Purdy, is regarded as one of

the premier golf courses in New Jersey. It is a par 70 - 6,483 yard course and “offers

one of the most breathtaking views in Morris County”.

 

NATURAL RESOURCES

 

New Jersey Landscape Project

 

The NJDEP completed the New Jersey Landscape Project (NJLP) in 1994 with the

primary goal “to protect New Jersey’s biological diversity by maintaining and

enhancing imperiled wildlife populations within healthy, functioning ecosystems”. By

combining imperiled and priority species location information with land-use/landcover

data, NJDEP was able to provide a comprehensive guide to allow individuals and

agencies to make ecologically responsible decisions regarding land-use in New Jersey.

It is important to note that the data contained within the NJLP was specifically

designed to function as a planning tool and carries with it no regulatory implications.

The Landscape Project divides habitat patches into five (5) critical area classifications

based on the number of occurrences of State or Federal priority, threatened and

endangered species. These critical area rankings are as follows:

Rank 5 Assigned to patches containing one or more occurrences of at

least one wildlife species listed as threatened or endangered on

the Federal list of endangered and threatened species.

Rank 4 Assigned to patches with one or more occurrences of at least one

State endangered species. (none in Pequannock Township)

Rank 3 Assigned to patches containing one or more occurrences of at

least one State threatened species.

Rank 2 Assigned to patches containing one or more occurrences of at

least non-listed State priority species.

Rank 1 Assigned to patches that meet habitat-specific suitability

requirements, such as minimum size criteria for endangered,

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

69

threatened or priority wildlife species, but that do not intersect

with any confirmed occurrences of such species

Of these five classifications, Rank 5 is the only one that does not exist within

Pequannock Township. Each rank is further divided by habitat type based on land

cover data. Five (5) distinct habitat types were identified within Pequannock

Township including: Forest, Grassland, Emergent Wetland, Forested Wetland, and

Wood Turtle Habitat. See map titled NJ Landscape Project (Maps 10-14). The

following are the critical area/habitat type combinations that can be found within

Pequannock Township.

 

Forest

 

Within Pequannock Township Rank 2, Rank 3, and Rank 4 priority areas within the

forest habitat were identified. The Rank 2 Priority Species forest is present as a single

patch within Aquatic Park at Pequannock Township’s Northwest corner. Rank 3

Forested Areas are present along much of Pequannock Township’s Western half and

encompass most of Rockledge Park and parts of Greenview Park.

 

Grasslands

 

Grasslands as defined by the New Jersey Landscape Project materialize within

Pequannock Township as of a single patch located just north of Route 504 and to the

West of West Parkway. This patch does not fall within any of Pequannock Township’s

existing parks.

 

Forested Wetlands

 

Forested wetlands, most of which are Rank 2, are found in abundance throughout

Pequannock Township. Rank 1 Forested Wetlands straddle Pequannock Township's

western border and are present minimally within Mountainside Park. Rank 2 Forested

wetlands are located throughout the township and are typically located adjacent to

the Pompton River as well as the East and West Ditches and are found in many of

Pequannock Townships Parks including Rockledge, Greenview, Cheery Street, Lyman,

Myers Brook, and Aquatic. It is important to keep in mind that although the NJLP does

not carry any regulatory weight, all areas identified as forested wetlands within

Pequannock Township are subject to NJDEP wetlands regulations.

 

Emergent Wetlands

 

Both Rank 1 and Rank 2 Emergent wetlands can be found minimally within Pequannock

Township. There is a small portion of Rockledge Park’s southwest corner classified as

Rank 1 while much of the northern boundary of Aquatic Park falls within this

classification. It is important to note that although these areas are not classified as

wetlands by NJDEP, they are likely to still exhibit some of the characteristics of

wetlands, such as poor drainage and wet soil.

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

70

 

Woodland Turtle Habitat

 

Much of Pequannock Township’s southwestern corner is comprised of Rank 3 Woodland

Turtle habitat for threatened species. The only park that this area is present in is

Rockledge Park which consists of about 95% of land classified as Rank 3 Woodland

Turtle Habitat.

 

Environmental Resource Inventory

 

In September 1995 Thonet and Associates completed an Environmental Resource

Inventory (ERI) with the help of the Pequannock Environmental Commission. This

Master Plan will summarize the environmental inventory findings from the ERI. The

ERI should be consulted for more detailed information. Inventory findings have been

augmented with data that has been made available since the ERI was completed.

 

Topography

 

The largest portion of Pequannock Township is very flat, having elevations that vary

between 180 and 200 feet above mean sea level. In the northwestern corner of the

Township from the western portion of Mountainside Avenue west elevations begin at

about 200 feet and climb up to 734 feet at the top of Pequannock’s Turkey Mountain,

aka Pequannock Knob. These high elevations provide excellent views of Pequannock

Valley and they are viewed from several locations within the Township.

 

Geology

 

Pequannock Township lies within the Mesozoic Piedmont and the Precambrian

Highlands New Jersey geographic provinces. The Ramapo Fault separates the

provinces in Pequannock (Map 15). The Ramapo fault is a series of smaller, parallel

faults running in as southwest-northeast strike. The oldest rocks found in Pequannock

are the Precambrian gneisses. Fine-textured sediments were deposited on the Glacial

Lake Passaic lake bottom forming an impermeable cap which confines Pequannock’s

subterranean aquifer, the source of most of the township’s drinking water (Map 16).

In Pequannock, pockets of till can still be found with giant boulders (glacial erratics)

on top of the peaks of the Highlands. The valley, however, is mostly filed with

fluvoglacial deposits dropped by torrential melt water streams and moraine-dammed

Glacial Lake Passaic sediments.

 

Soils

 

Soils in Pequannock Township range from gravely stony soils to mucky soils (Map 16).

Approximately fifty-two percent (52%) of the soils in Pequannock Township are

classified as Urban Lands, are part of the Riverhead-Urban land-Pompton association,

whose boundaries generally conform to the developed areas within the Township.

These soils consist of wet organic soils, wet clayey soils, and wet or dry gravelly sandy

loams. They are underlain by stratified or lacustrine sediment are in basins, on low

plains, or on terraces. This association consist of deep, well drained to somewhat

poorly drained, nearly level or strongly sloping gravelly sandy loams and sandy loams

that overlie stratified outwash sand and gravel on outwash plains and terraces. The

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

71

Pompton and Riverhead soils are in the higher elevations within the low-lying areas in

the western section of the Township.

Approximately fifteen percent (15%) of the soils are part of the Rockaway-Hibernia-

Urban land association. These soils are deep, well-drained to somewhat poorly

drained, gently sloping to steep gravelly sandy loams and stony to extremely stony

loams and sandy loams that overlie granite gneiss on uplands. These soils are

generally found in the northwest section of the Township in the area of Mountainside

Park.

Approximately twelve percent (12%) of the soils in the Township are in the Carlisle-

Parsippany-Preakness association. This association was also formed in glacial land

sediment or outwash. Soils in this association are deep, poorly drained and very

poorly drained, nearly level mucks silt loams, and sandy loams that overlie stratified

lacustrine sand, silt, and clay or stratified outwash sand and gravel in depressions or

along low-gradient streams.

The following is specific soils information regarding the sites identified in the Open

Space and Recreation Plan as possible for athletic fields.

 

Rockledge Park

 

CarAt-Carlisle muck, frequently flooded (85%) , frequent ponding (saturating soil up to

one (1) foot in depth, for long periods of time except in July and August, brief

flooding, high water table at grade.

PrkAt – Preakness sandy loam – poorly drained brief flooding and ponding year round

lasting for brief periods (saturating soil up to one(1) foot depth), depth to high water

table at to 6” below grade.

PrsdAt – Preakness dark surface variant sandy loam – rarely occurring, long lasting

periods of ponding year round (saturating soil up to 0.4’ depth), frequent but brief

periods of flooding year round, high water table at grade to 6” below grade.

 

Aquatic Park

 

PbphAt – Parsippany, sandy loam substratum – Frequent periods of flooding and

ponding in the spring lasting for brief periods (saturating soils up to one (1) foot

depth), occasional periods of ponding for brief periods and no flooding in the fall, high

water table at to one (1) foot below grade in the fall to spring with the high water

table dropping to one to two feet below grade in July and August.

 

Riverside Park

 

UR – Urban land – No flooding.

 

Lyman Park

 

CarAt-Carlisle muck, frequently flooded (85%) , frequent ponding (saturating soil up to

one (1) foot in depth, for long periods of time except in July and August, brief

flooding, high water table at (above) grade.

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

72

 

Woodland Lake

 

PrkAt – Preakness sandy loam – poorly drained brief flooding and ponding year round

lasting for brief periods (saturating soil up to one(1) foot depth), depth to high water

table at to 6” below grade.

USHRVB – Urban Land – Not flooded., not rated.

UR –Urban Land – not rated

 

Hydrology

 

Pequannock Township’s principal open waters include the Pequannock River, the

Pompton River, East Ditch, West Ditch, and Sawmill Creek. The Pompton River is

formed as the Pequannock and Ramapo Rivers converge, and flows southerly for about

seven miles into the Passaic River in Lincoln Park. It marks the eastern boundary of

the Township of Pequannock and the Pequannock, Ramapo, Wanaque River and

Pompton Rivers are all tributaries of the Passaic River (Map 17).

Pequannock Township sits atop three distinct watersheds; the Pompton River, which

comprises approximately 90% of the Township’s area , the Pequannock River which

comprises a great majority of the remaining area along the Township’s northern

border, and the Ramapo River Watershed which occurs minimally at the Pequannock’s

northwestern corner.

Development implications related to Pequannock Township’s surface hydrology include

regulations regarding flood hazard areas, net fill, trout production waters and

wetlands. Regulations regarding groundwater hydrology include community wellhead

protection areas.

 

Surface Hydrology

 

Low lying areas of Pequannock are subject to periodic flooding caused by the overflow

of the Pompton, Pequannock, and Ramapo Rivers, the East and West Ditches and

tributaries to the East Ditch.

Food hazard areas: The floodway is the channel of a stream/river, plus any adjacent

flood plain areas, that must be kept free of encroachment so that the 100-year flood

can be carried without substantial increases in flood heights. The area between the

floodway and NJDEP’s Flood Hazard Area boundaries is termed the flood fringe. The

flood fringe encompasses that portion of the flood plain that could be completely

obstructed without increasing the water surface elevation of the 100-year flood more

than 0.2 foot at any point, with such encroachment not increasing the magnitude of

the peak flows. Map 18 identifies the flood hazard areas within the Township.

Net fill: Grading during land development is regulated along open waters. In the

Central Passaic Basin, grading must not exceed zero net fill (overall soil quantities

must meet existing volume prior to development), and for the remaining food plains in

the western part of the Township north of Jacksonville Road, the maximum net fill

allowance is twenty percent.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

73

Trout production waters: All of the streams in Pequannock are classified by NJDEP as

Fershwater-2 Non-Trout (TW2-NT) waters. In all FW2-NT waters, the designated uses

are:

1. Maintenance, migration and propagation of the natural and established biota;

2. Primary and secondary contact recreation;

3. Industrial and agricultural water supply;

4. Public potable water supply after such treatment as required by law or

regulation;

5. Any other reasonable uses.

 

Groundwater Hydrology

 

Groundwater is subsurface water occurring in fully saturated soils and geologic

formation, not as isolated bodies of underground water, but rather as integral parts of

the hydrologic cycle (see the ERI for more details on the hydrologic cycle). Map 19

identifies the differing rates of groundwater recharge in the Township.

Community Wellhead Protection Areas: A Well Head Protection Area (WHPA) in New

Jersey is a map area calculated around a Public Community Water Supply (PCWS) well

in New Jersey that delineates the horizontal extent of ground water captured by a

well pumping at a specific rate over a two-, five-, and twelve-year period of time.

WHPA delineations are conducted in response to the Safe Drinking Water Act

Amendments of 1986 and 1996 as part of the Source Water Protection Program

(SWAP).

 

Water Supply

 

Pequannock Township acquires their water from 4 sources; 3 high volume wells,

Newark Water Supply Aqueducts, Lincoln Park, and Riverdale. The Township relies on

the 3 wells for 96 % of its water supply. The wells are located in the north portion of

the Township. The Newark Water Supply Aqueducts are use for a back up to the wells

as well as the connection to Lincoln Park’s water supply. The Riverdale’s water supply

connection is used as an emergency connection. Map 20 locates the Township’s water

supply wells and the aquifers underlying the Township.

 

Wastewater Disposal

 

Pequannock Township is serviced by the Two Bridges Sewer Authority that is located in

Lincoln Pak. Many of the homes are not connected to this sewer system and rely on

septic systems. With in the township there is only one treatment plant located at the

Plains Plaza Shopping Center, however this is a privately owned facility to be used only

by the shopping center.

 

Land Cover

 

Pequannock Township is considered fully developed. Those lands that are not

developed have environmental constraints associated with them. Map 21

identifies the different land cover types within the Township.

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

74

 

Vegetation and Wildlife

 

Forest

 

The natural vegetation in Pequannock is typical for the geographic region with four

types of forest that are prevalent within the town. Chestnut forest, mixed oak forest,

sugar maple hardwoods forest, and hemlock mixed hardwoods forest; each with their

on distinctive characteristic. The chestnut forest is found in the highlands region along

ridge tops, slopes, and outcroppings. The mesic uplands is the area were the mixed

oak forest, sugar maple hardwoods forest, and hemlock mixed hardwoods forest are

found. Further information on what type of vegetation in the types of forest can

found in Pequannock Township Environmental Resource Inventory.

 

Wetlands

 

Wetlands means those areas that are inundated or saturated by surface or

groundwater at a frequency and duration sufficient to support, and that under normal

circumstances do support, a prevalence of vegetation typically adapted for life in

saturated soil conditions. Wetlands generally include swamps, marshes, bogs, and

similar areas. Wetlands play an essential role in the overall well being of the

environment and provide natural habitats. Approximately 16% of Pequannock Township

is wetlands most of which are protected open space.

 

Wildlife

 

The Wildlife found in Pequannock is typical for the geographic region, a list of specific

species can be found in Pequannock Township Environmental Resource Inventory. The

variety and abundance of wildlife population is a clear indicator that other aspects of

the natural environment are relatively stable. According to New Jersey Department

Environmental Protection (NJDEP) there are woodland turtles within Pequannock

which are a threatened and endangered species. There are several federal and state

regulations protecting the woodland turtle and its habitat including the Endangered

Species Act (ESA) and the Habitat Conservation Plans (HCP).

 

Existing Parks Developable Lands

 

An evaluation of the natural resources of the existing park lands has identifies several

environmental factors that will impact the ability to expand existing facilities or

develop currently undeveloped park lands. These environmental factors include

wetlands, steep slopes and floodway locations. Each of these factors has regulations

restricting development in areas where they are located. Table 7 identifies these

constraints per park and the overall impact on the amount of land available for

unrestricted development.

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Table 7 ~ Environmental factors effecting park land development

 

The fertile valley at the confluence of three rivers that was so appealing for settlers

brings with it the associated river floodways and wetlands. The majority of the

Township’s park lands are greatly affected by these environmental factors. Only those

facilities centrally located in the Township are unaffected. In general, wetlands may

not be filled or altered. The development of trails, however, is permissible by permit

from the New Jersey Department of Environmental Protection (NJDEP). No

development is allowed within floodway limits. Steep slopes may be regulated by

ordinance as well as best management practices and in this instance the Highlands

Act.

 

AIR QUALITY

 

Air pollution has been a growing concern among many environmentalists within the

last several decades. With words such as greenhouse gases, the ozone, and global

warming becoming part of everyday conversation within the past several years a vaster

segment of the population is concerned about air quality. New Jersey air quality has

improved since the passage of the Clean Air Act in 1970. One of the major pollutants

that remains a concern in New Jersey in acid rain with pH level ten times higher then

that which naturally occurs. To date there are no regulation to set an air quality

standard for acid rain.

 

NOISE LEVELS

 

Noise is classified as a pollutant because by definition it is an unwanted sound and can

affect the health and well being of people and the enjoyment of property. The three

leading causes of noise are Route 287, Route 23, and Lincoln Park Airport.

 

CONTAMINATED SITES

 

Pequannock Township has 21 contaminated sites as listed in the NJDEP

publication Known Contaminated Sites in New Jersey, 7th edition. The sites

listed are confirmed to have soil and/or groundwater contaminants.

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

75

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

76

 

CONNECTIVITY OF OPEN SPACE SYSTEM

 

Pequannock Township’s open space system lacks a cohesive connective system such as

a greenway system or bicycle paths. The parks, board of education properties,

township owned lands, other public lands, cultural resources, and environmental

resources are not distributed evenly throughout the township.

The majority of the parks within the Township are located in the central to southern

area of the town. The two largest parks Mountainside Park and Aquatic Park are

located in the northern portion of the Township and both parks are separated from the

town by a major roadway, interstate highway 287 separates Mountainside Park and

Route 23 separates Aquatic Park. Mountain Avenue is the only access to Mountainside

Park within Pequannock. No other access is available within the town due to interstate

highway 287 traversing the northwest corner of Pequannock Township. Aquatic Park

located in the northeast corner of the township is separated from the nearest

residential neighborhood by Route 23 with no pedestrian access other then crossing

the highway. The other parks are within the residential neighborhoods and are

relatively accessible to the community.

The schools are evenly distributed throughout Pequannock with the elementary

schools in the northern, central, and southern sections and the Middle and High

schools are centrally located.

The County owned Sunset Valley Golf Course is located on the west side of the

township with part of the course in the Borough of Kinnelon. The entrance to the golf

course is located on West Sunset Road within a residential neighborhood.

The cultural resources of the Pequannock refer mainly to the historic sites. These sites

are located throughout the Township with a majority of the site located on Newark

Pompton Turnpike.

Pequannock has a verity of environmental resources from the 720-foot vertical peek at

Mountainside Park to the Pompton and Pequannock rivers that create the natural

eastern border of the township. The largest of these environmental resources are the

preserved wetlands. The wetlands play an integral part in the environmental well

being of not only the town but the inter state. These preserved areas are sanctuaries

for wildlife within the ever-expanding urban environment. The wetlands also act as a

natural filter for storm water prior to the water entering the second largest

environmental resources of the township the rivers, streams, lakes, and ponds. These

water bodies are both a fundamental part of the uniqueness of Pequannock as well as

the town’s park system. Sixty percent of the parks are associated with one or more of

these water bodies. The vitality of these water bodies is also important to the entire

state because they provide refuge for migrating waterfowls and other wildlife. The

variety of environmental resources are also an excellent educational tool for the

residents of Pequannock.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

77

Although Pequannock Township has an array of open space resources, one critical

element is missing. A cohesive path/ trail system to link Pequannock open space

elements together. Several systems can be used to fill this void such as a greenway or

bicycle path. The goal of the path system is to link the varies open spaces making

them assessable by walking or bicycle, therefore eliminating the necessity of

Pequannock residence to drive in order to enjoy the open spaces of the Township.

A greenway is a multi-purpose linear route usually a railroad right-of-way that is no

longer used and converted into a pedestrian and cyclist thoroughfare. The unused New

York Susquehanna Western Railway Corporation rail line, which traverses the eastern

section of the Township from the northern boarder between Pequannock and Riverdale

heading southward parallel to Newark Pompton Turnpike and crossing the Pompton

River into Wayne near Pia Costa Lake at the southern boarder between Pequannock

and Lincoln Park. Currently the land is owned by the New York Susquehanna Western

Railway Corporation. The Township should look at acquire the land because this would

be ideal for the much needed greenway. The conversion of this property in to a

greenway would also assist the Morris County in realizing their goal of establishing a

multi-use trail system in this section of the county.

Another way to define a greenway is a street connected in a network throughout the

city, which is enhanced to provide a pleasant environment for pedestrians and cycling.

A greenway of this type would coincide with the proposed trail system in the Township

master plan, illustrated on appendix MPA #1. Six streets should be converted in to this

type of greenway, Newark Pompton Turnpike, West Franklin Avenue, Ackerson

Avenue, Mountain Avenue, Sunset road, Ackerson Avenue, and West Parkway. Turning

these streets into greenways would enable the parks, cultural and environmental

resources, and schools assessable for pedestrians and cycling directly from one of

these roads or with a short walk. West Parkway should have a bicycle lane in

conjunction with the County’s plan to link to an existing bicycle trail in Riverdale,

although this plan has been rejected by the residence on this road in the past.

 

Chapter 5 - Inventory and Analysis of Existing Resources

PENNONI ASSOCIATES INC.

Consulting Engineers

 

78

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Foothills Park

Rockledge Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

N.J. Landscape Project

 

Legend

 

Pequannock Township

Park Boundaries

Roads

Lakes

Streams

 

Forest

 

Rank 2

Rank 3

Rank 4

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 10

 

Forest

 

79

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Rockledge Park

Foothills Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

N.J. Landscape Project

 

Legend

 

Pequannock Township

Park Boundaries

Lakes

Streams

Roads

Rank 1

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 11

 

Grassland

 

81

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Rockledge Park

Foothills Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

N.J. Landscape Project

 

Legend

 

Pequannock Township

Park Boundaries

Lakes

Streams

Roads

 

Emergent

 

Rank 1

Rank 2

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 12

 

Emergent Wetlands

 

83

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Foothills Park

Rockledge Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

N.J. Landscape Project

 

Legend

 

Pequannock Township

Park Boundaries

Lakes

Streams

Roads

 

Forested Wetlands

 

Rank 1

Rank 2

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 13

 

Forested Wetlands

 

87

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Rockledge Park

Foothills Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

N.J. Landscape Project

 

Legend

 

Pequannock Township

Park Boundaries

Lakes

Streams

Roads

 

Wood Turtle

 

Rank 3

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 14

 

Wood Turtle Habitat

 

85

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

( ( ( ( ( ( ( (( ( (

(

( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (

( ( ( ( ( ( ( ( ( ( ( ( ( ( (

 

! ! ! ! ! ! ! !

!

 

Pyroxene

Gneiss

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Foothills Park

Rockledge Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park Boonton Formation

Quartz

pebble

Conglomerate

 

eiss

 

Amphibolite

Quartz

Oligoclase

Gneiss

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

Geology Map

 

Legend

 

Pequannock Township

Park Boundaries

Lakes

Streams

Roads

Province Boundary

 

Geology

 

Amphibolite

Boonton Formation

Pyroxene Gneiss

Quartz-Oligoclase Gneiss

Quartz-pebble Conglomerate

 

! ! folds

 

( ( faults

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 15

 

Highlands Province

Piedmont Province

 

89

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

USRHVB

UR

UR

CarAt

PrsdAt

UR

RNRE

USPREB

RNRE

PHG

OtsD

OtsC

PHG

UR

RNRE

PafAt

PbphAt

OtsC

PrsdAt

PafAt

BohC

RobCb

CarAt

HhmCa

RobCb

HhmCa

RomD PohA

FNAT

WATER

HhmCa

PohA

WATER

PrkAt

PafAt

RksA

BohC

RksB

RkgBc

RksA

PbphAt

WATER

RomC

RksB

PawE

Dc

RomC

PohB

PrkAt

RobCb

RkgBc

USROCC

RobCb

PohA

PrkAt

RksB

OtsC

RomC

PrkAt

bCb

PohB

OtsC

PbphAt

PohB

PbphAt

BohC

PohB

PohB

PrkAt

RksC

CarAt

OtsC

WATER

PrkAt

RksC

AdrAt

PrkAt

PohB

AdrAt

PrsdAt

PbphAt

PohA

BohB

OtsC

HhmDb

PHG

WkkAt

PohA

PohA

HanC

HhmCa

HhmDb

OtsD

RomE

WATER

PrkAt

PohB

USRHVB

RksB

OtsC

RomD

OtsD

BohB

PafAt

RobDc

PrsdAt

PrkAt

BohB

BohB

WATER

WATER

RomD OtsC PrkAt

PohB

PafAt

RksB

AdrAt

PrkAt

WATER

PohB

RobDc

HanB

RksB

PrsdAt

RobDc

WATER

PrkAt

WATER

WATER

WATER

WATER

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

Soils

 

Legend

 

Pequannock Township

Lakes

Streams

Roads

 

Soils

 

AdrAt

BohB

BohC

CarAt

FNAT

HanB

HanC

HhmCa

HhmDb

HokCg

MknA

NerB

NerC

OtsC

OtsD

PHG

PafAt

PawE

PbphAt

PohA

PohB

PrkAt

PrsdAt

RNRE

RkgBb

RkgBc

RksA

RksB

RksC

RobCb

RobDc

RomC

RomD

RomE

UR

USPREB

USRHVB

USROCC

WATER

WkkAt

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 16

 

91

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

POMPTON RIVER (WANAQUE)

RAMAPO RIVER

RAMAPO RIVER (WANAQUE)

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Rockledge Park

Foothills Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

EAST DITCH

WEST DITCH

POMPTON RIVER (WANAQUE)

POMPTON RIVER

WEST DITCH

EAST DITCH

EAST DITCH

EAST DITCH

EAST DITCH

EAST DITCH

POMPTON RIVER

POMPTON RIVER (WANAQUE)

POMPTON RIVER

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

Hydrology Map

 

Legend

 

Pequannock Township

Park Boundaries

Roads

Lakes

Streams

 

Subwatershed

 

Lincoln Park tribs (Pompton River)

Pequannock R (below Macopin gage)

Pompton River

Ramapo R (below Crystal Lake bridge)

 

Watershed

 

Pequannock River

Pompton River

Ramapo River

Wetlands

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 17

 

93

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Foothills Park

Rockledge Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

Groundwater Recharge

 

Legend

 

Pequannock Township

Park Boundaries

Lakes

Streams

Roads

 

Groundwater Recharge Rate

 

0.00 - 4.99

5.00 - 9.99

10.00 - 14.99

15.00 - 19.99

20.00 and >

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 19

 

97

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

&< &<

 

&< &<

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Foothills Park

Rockledge Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

Not a SSA

Highlands

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

Aquifers Map

 

Legend

 

Pequannock Township

Park Boundaries

Roads

Lakes

Streams

 

&< Public Community Water Supply Wells

Surfical Aquifer

 

Sole Source Bedrock Aquifer

 

Highlands

Not a SSA

Ramapo

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 20

 

99

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Mountainside Park Aquatic Park

Woodland Lake

Lyman Park

Greenview Park

Foothills Park

Rockledge Park

Hidden Cove Park

Meyers Brook

Washington Park

Hillview Park

Cherry Street Park

Pequannock Valley Park

Town Hall Fields

Riverside Park

Lyon Park

 

NJ 23

ROUTE 504

ROUTE 511 ALTERNATE

SUNSET RD

MORRIS COUNTY 660

MOUNTAIN AVE

BEAVER BROOK RD

WEST PARKWAY

MANDEVILLE AVE

ALEXANDER AVE

MORRIS COUNTY 680

MORRIS COUNTY 635

HOPPER AVE

 

Pequannock Township

Recreation Master Plan

 

Land Cover (2002)

 

Legend

 

Pequannock Township

Park Boundaries

Lakes

Streams

Roads

 

Land Cover

 

AGRICULTURE

BARREN LAND

FOREST

URBAN

WATER

WETLANDS

 

0 0.25 0.5 0.75 1

Miles Ż Information Sources:

New Jersey Department of Environmental Protection

Bureau of Geographic Information Systems

http://www.nj.gov/dep.gis/index.html

 

Map 21

 

101

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Chapter 6 – Benchmark to Similar

Recreation Systems

 

This master plan took a look at the recreation facilities that the adjacent

municipalities provide and municipalities in Morris County that were similar to

Pequannock Township (see Table 8). The similar communities were selected based

upon similar population, median family income and municipal area. Pequannock

Township provides recreation facilities similar to both benchmark groups. The

Township also has the opportunity to provide recreation opportunities that the other

municipalities don’t due to Pequannock Township’s location along rivers and at the

base of the mountains.

 

Table 8 ~ Benchmark communities recreation amenities.

 

The conclusion is that while Pequannock Township has a need for athletic fields, the

recreational facilities the Township provides is at a level similar to the benchmark

communities.

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

103

 

Chapter 6 – Benchmark to Similar Recreation Systems

PENNONI ASSOCIATES INC.

Consulting Engineers

 

104

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

105

 

Chapter 7 – Acquisition, Capital

Improvement and Maintenance

Recommendations

 

Pequannock Township has preserved a large quantity of the Township’s lands for

recreation use. The lands that are not currently developed are limited in the type of

development that can occur due to their location within the floodway or 100 year

floodplain or due to wetlands or steep slopes. These lands are regulated through

NJDEP and the NJ Highlands regulations. Opportunities, however, remain to address

the gap in parks and facilities. The greatest opportunities lie in redeveloping and adding

lands to existing parklands.

 

Existing Park Lands and Adjacent Land Acquisitions

 

Aquatic Park

 

A master plan was completed for Aquatic Park in 2004 where development

recommendations were made. This Master Plan makes recommendations to build upon

the previous recommendations. A new parking area was recommended in the Master

Plan at the Rt. 23 jug handle across from the Newark-Pompton Turnpike. This location

is feasible should the New York & Susquehanna Western Rail Road line be discontinued

and the right of way available for use as a regional trail network. Currently extensive

measures would have to be taken to safely convey users across the right-of-way either

at grade or under the tracks.

There currently is ATV use in several areas within the park. This use is not permitted

and is degrading the sites environmental conditions. More stringent enforcement is

needed. To do so, however, required better access. The site currently has access from

Carlson Place, which is limited due to no parking provided. In addition, with encroaching

uses from the south, potential park users may not be aware of what is park land and

what is private lands.

Opportunities exist for trail development, canoe portage points and camping areas.

Active recreation opportunities are not recommended for the existing parklands due to

poor access and the sensitive nature of the lands (wetlands, floodway and floodplain)

and the regulations imposed on these lands.

An opportunity exists, however, to expand the park to the south with the acquisition of

Block 306 Lot 4. The majority of this site is not impacted by wetlands and is fairly level

and would be suited for development as an athletic field. The site appears to support a

full size soccer/lacrosse field with parking for 120 cars. This parking could also serve as

trail head parking for the Park with entrance kiosk and map box (see map titled Aquatic

Park Concept Plan). The sites wetlands should be mapped to confirm their location and

ability to develop the parcel. Development of the site would require NJDEP permits.

This site provides one of the few opportunities to add athletic fields in Pequannock

 

Chapter 7 - Acquisition, Capital Improvement and

Maintenance Recommendations

PENNONI ASSOCIATES INC.

Consulting Engineers

 

106

 

Township. If acquisition is not feasible then exploration of an agreement with the current

owner may be able to be reached to allow the Township to use the land for a

soccer/lacrosse field.

Aquatic Park Program Elements

 

? 1.5 miles of trail development

 

? Land acquisition

 

? Soccer/lacrosse field development

 

? Parking lot development (two locations)

 

? Canoe portage

 

Cherry Street Park

 

According to NJDEP GIS mapping the majority of the site has wetlands and thus is

regulated by NJDEP. There is an apparent pocket with no wetlands by New Street. The

site is within the 100 year floodplain. The eastern border of the site abuts the New York

Susquehanna & Western Railway Corporation rail line. Washington Park lies across

Jefferson Street to the north. The Township owns four smaller parcels to the south of

the Park. These smaller parcels are also affected by wetlands.

This site can be developed with trails that can be a loop walking trail and connected to

New Street, Jefferson Street and the adjacent residences. NJDEP permits will be

required for development. Future connection to the railroad ROW can also occur should

that line be developed as a greenway trail. The smaller lots to the south (Block 3608

Lots 1, 4, 5 &6) should be added to the Township’s ROSI.

The Open Space and Recreation Plan recommended acquisition of two other lots ( Lot 2

& 3). These lots are adjacent to Cherry Street Park. They currently have a swimming

pool located approximately on the joint property line of the two lots. These lots appear

not to have wetlands associated with them. Should the land become available the

Township should pursue acquisition, as it would fill in between the main portion of the

Park and the smaller lots. Acquisition of these lots is not recommended at this time.

Cherry Street Park Program Elements

 

? 1.5 miles of trail development

 

Foothills Park

 

The park is currently underutilized. There is a playground, parking and a cleared area

that is used for sledding in the winter. There is a small pond with a steep drop from the

south to the pond and according to NJDEP GIS mapping a small amount of wetlands to

the east of the pond. There are steep slopes along the northern border of the park. The

police have a training facility in the western section of the site cuts off access to the

northern and western portions of the site, thus leaving half of the park unused.

There is potential for development of this site to fulfill its role as a neighborhood or

community park and satisfy a portion of that need. To do this the northern and eastern

portions of the site need to be easily accessible to the residents. Long range the police

training facility should be removed from the park. Upon the discontinuing of the police

training facility the parking area may be relocated and a U-10 soccer field placed in that

area overlapping part of the existing parking.

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

107

 

A paved loop walking/exercise path should be developed passing by the pond and

encircling the eastern area of the park. This will provide opportunities for exercise and

nature study of the pond and wetland ecosystem with the inclusion of an overlook. A

community center can be developed in the eastern portion of the site with some parking.

See conceptual programming and footprint options. The community center building can

utilize the topography of the site to enter on the second level with parking built into the

hillside similar to other adjacent development. The community center would provide

opportunities for community events and a facility that would support the indoor recreation

and leisure programming that is currently offered.

A second possible location for the community center would be to the south of the parking

and playground area of the park. The top of the hill is relatively flat and access from

West Parkway can occur at the southern property line where the site and roadway grade

are compatible. Care should be taken to preserve as much of the sledding hill as

possible.

The upper area in the southwest section of the park can be developed as a U-10 soccer

practice area with the parking area expanded.

The pedestrian connection to the park needs to be improved though either a greenway

network including a sidewalk that can safely direct people to the park from the

residences to the south.

Foothills Park Program Elements

 

? 0.2 miles of trail development

 

? Paved walking trail

 

? Overlook

 

? Soccer practice field (U-10)

 

? Parking lot expansion

 

? Community Center

 

? Remove police training facility

 

Greenview Park

 

Greenview Park serves Pequannock and the neighborhood as a community park. It has

a wide variety of recreation and leisure opportunities. There is a deficit, however, of

parking to meet the provided facilities.

The parking demand was evaluated and it was found that there currently is a deficit of

seventy (70) parking spaces. This Master Plan presents, therefore, a recommended

parking and facility reconfiguration. The western parking lot would be restriped and

slightly expanded to improve efficiency. A new parking lot would be provided from the

entry off of Colfax Drive. The existing parking by the pond would be slightly expanded

and restriped. The parking lot by the tennis courts and the softball fields will be

expanded to the south slightly which will allow for a more efficient layout and increase

the number of parking spaces. In addition, the existing culvert from the Roberts Place

entrance should be lengthened to allow for two way traffic.

 

Chapter 7 - Acquisition, Capital Improvement and

Maintenance Recommendations

PENNONI ASSOCIATES INC.

Consulting Engineers

 

108

 

The connecting roadway between the parking near the pond and the parking near the

tennis courts is removed. This opens up the center of the park for more activities such

as a picnic shelter, spray pad and a playground. These new central uses support the

existing uses and allow opportunities to spend the entire day at the park.

The playground area would be developed when the existing playground structure

needed to be replaced. Short term the poor drainage at the existing playground needs

to be addressed.

Expansion of the existing lacrosse field to the east of the tennis courts is not feasible due

to the location of wetlands in the adjacent woods and the area being identified as

possible habitat for the wood turtle.

Greenview Park Program Elements

 

? Parking lot reconfiguration and addition

 

? Roadway paving and curbing

 

? Existing playground drainage

 

? Picnic shelter and tables

 

? Spray pad

 

? Playground

 

? Pedestrian walkways

 

? Landscaping

 

Hidden Cove

 

The majority of area within Hidden Cove is open waters. Hidden Cove is used for

fishing. As it is contiguous with a swimming facility to the south the open water cannot

be used for boating. There is poor access to the site. No parking is provided on site

and the owner of the adjacent parcel will not allow shared parking. Users must park

across busy Lincoln Park Road and walk across.

A small parking lot of approximately six (6) parking spaces should be developed. Trails

should be formalized to the water’s edge. Trails to the west of the pond would most

likely be within wetlands and would require a permit. Fish habitat should be improved

with additional plantings that would eventually overhand the pond edge and

sunken logs and aquatic vegetation as places for fish to hide.

Hidden Cove Program Elements

 

? Six car parking lot

 

? 0.2 mile trail development

 

? Fish habitat enhancement

 

Hillview Fields

 

This facility is the best location to develop into a higher-use athletic facility. Community

uses are adjacent to seventy five percent (75%) of the site (two schools and the library)

and single family residential is adjacent on the remaining portion.

The site is heavily used for softball, baseball, soccer and lacrosse. Due to the demands

for athletic fields the fields do not have any time to rest the grass and as such the grass

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

109

 

is in poor condition. It is unlikely that unless the fields are allowed to rest and receive

irrigation that they would be of the quality that the Township wants to provide it’s

residents. Recommendations for Hillview fields include the installation of synthetic turf

and sports lighting.

Hillview Fields Program Elements

 

? Synthetic turf

 

? Sports lighting

 

Lyman Park

 

According to NJDEP GIS data wetlands can be found throughout most of Lyman Park.

The portion of the park that appears to not have wetlands is in the central area, a portion

of which is cleared of trees. This cleared area may be used for soccer practice. The

wetlands can also be mapped to see if the field area may be enlarged.

The site is located within the 100 year floodplain and has poor drainage. To maximize

the field use subsurface drainage should be installed. Parking is currently available at

the end of the entrance road off Roosevelt Street.

Two adjacent lots (Block 4112 Lots 1&16) have been identified in the Open Space and

Recreation Plan for possible acquisition. Both of these parcels would be developable, at

least in part, for single family homes. It is unlikely, however, that they may be developed

for recreational use other than for trails due to wetlands and open waters on both sites.

These two parcels should be acquired to preserve these sensitive lands and increase

Lyman Park’s area.

Lyman Park Program Elements

 

? Wetlands mapping

 

? Open field expansion for athletic practice field

 

? Expand trail network to 0.5 miles of trails.

 

Lyon Park

 

This is a small mini-park with a playground and benches. The playground equipment

should be evaluated to conform to CPSC standards and upgraded if non-conforming.

This park would also benefit from the addition of picnic tables.

Lyon Park Program Elements

 

? Playground equipment

 

? Picnic tables

 

Meyers Brook

 

Meyers Brook is an open water stream with a small buffer that runs along the backyards

of single family homes. This park should remain in it’s natural condition with periodic

maintenance for the removal of debris and hazardous trees.

Meyers Brook Program Elements

 

? Open waters stream and buffer

 

Chapter 7 - Acquisition, Capital Improvement and

Maintenance Recommendations

PENNONI ASSOCIATES INC.

Consulting Engineers

 

110

 

Mountainside Park

 

Mountainside Park has great views of Pequannock and the surrounding valley. The

purchase of these properties preserved the ridgeline of the Waghaw Mountain and the

aesthetics and water quality for those in the valley below. The recently passed

Highlands Regulations has placed Mountainside Park in the Highlands Preservation

Area. This designation greatly limits the possible development of trails and supporting

facilities such as parking. Trails must be developed utilizing the native soils. It is

unlikely that the parking area will be able to be expanded as no new impermeable

surfaces may be added and gravel is interpreted as impermeable.

This being said, the trail network north of the parking area provides a varied experience

and overlooks of the valley below. A camping area is also located in this area.

Opportunities exist to add interpretive signage along the trails and at overlooks

describing the natural features and historic significance of the area.

There are no apparent trails south of the parking area. This Master Plan recommends

evaluation of this area of Mountainside Park for trail development. Criteria for

development should include unique geological features, land forms or vegetation.

Should no unique features be found the area is recommended to remain in it’s natural

state.

A larger, two sided, folded map should be developed consistent with trail system and

should include topography to aid in the trail user. The map should identify points of

interest. Descriptions of the points of interest should be included. It should be

developed to be reproduced in color and in black and white. The map could include a

brief description of the Waghaw Mountains and its history, the flora and fauna and the

various recreational opportunities within the park.

Mountainside Park Program Elements

 

? 4 miles of trails

 

? Parking area

 

? Camping area

 

? Interpretive signage

 

? Revised trail map

 

Pequannock Valley Park

 

Pequannock Valley Park is the only swimming facility in Pequannock Township. The

facility is heavily used providing a lake with open swim and swim meets, beach,

playground, basketball court and bathhouse. These facilities are in good condition. The

entire facility, however, is in need of updating to provide new amenities to continue to

draw members.

A dam at the eastern end of Woodland Lake creates the pond used for swimming at

Pequannock Valley Park. The dam currently is in need of repair in the next couple years

that will cost $400,000 (in 2005 dollars). The repairs would be good for approximately 5

years, then additional repairs are likely.

A master plan specifically for Pequannock Valley Park should be completed the first year

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

111

 

that would evaluate other aquatic complex amenities that could be provided. The master

plan should include a guest services plan and market feasibility analysis. It is critical, as

part of this work, to assess the current operating profile as well as the future operating

potential given an enhanced product and expanded revenue streams.

Pequannock Valley Park Program Elements

 

? Master Plan

 

? Swimming lake

 

? Swimming lanes

 

? Beach

 

? Playground equipment

 

? Basketball court

 

Riverside Park

 

This park provides an opportunity for neighborhood children to play on playground

equipment and enjoy nature. Similar to Lyon Park, the playground equipment should be

evaluated to conform to CPSC standards and upgraded if non-conforming. This park

would also benefit from the addition of picnic tables.

The Open Space and Recreation Plan recommend the addition of three parcels to this

park, Block 4403/Lot 1, 2 & 3. Block4403/Lot 1 plan would make a good addition to

Riverside Park. Two of the three lots are privately owned (Lots 1 & 2). According to

NJDEP GIS data a portion of Lot 2 and all of Lot 3 are within the Pompton River

floodway and all of Lot 1 and the remaining portion of Lot 2 are within the 100-year flood

plain. The parts of the properties within the floodway would not be able to be developed

do to environmental restrictions. The developable area on these lots would support a

small playground and a U-10 soccer field based upon spatial data only. Topographic

information was not available for review. Further feasibility of this site for development

as a practice location should be completed to determine final acquisition

recommendation.

Riverside Park Program Elements

 

? Playground equipment

 

? Picnic tables

 

? Feasibility study

 

Rockledge Park

 

The Township Open Space and Recreation Master Plan recommended two Township

owned parcels be added to the existing park holdings. The Township implemented this

recommendation.

According to NJDEP GIS data wetlands are located on the majority of this site. Even

with the regulation restrictions that go along with the wetlands this park would be good to

develop as a neighborhood park as there are two potential areas, east of Farm Road

and east of Copley Court, that appear to be non-wetlands. Both of these areas are

currently cleared and if they are not wetlands, may be used for athletic fields, playground

and/or parking. It is recommended that wetlands mapping be completed for these two

areas.

 

Chapter 7 - Acquisition, Capital Improvement and

Maintenance Recommendations

PENNONI ASSOCIATES INC.

Consulting Engineers

 

112

 

The area east of Copley Court is large enough to support a U-10 practice soccer field,

small playground equipment and a small parking lot in the current clearing. The size of

development is likely smaller with a required fifty foot (50’) buffer minimum around all

wetlands. The area east of Farm Road may be used for picnicking or a small practice

field. In addition, hiking trails/boardwalks should be developed as a loop trail with

connections to the four directions.

The entire park is also within the 100 year floodplain and has been identified as possible

wood turtle habitat. There is a restriction on having to balance soil moving done on site.

In addition, a study may have to be completed to verify whether wood turtles, a New

Jersey threatened species, are found on the site. If they are then the entire park may

not be developable, even for trails.

There is currently a basketball hoop installed on the eastern side of Farm Road terminus

cul-de-sac. If this is a Township facility it should be moved out of the roadway and if it is

not a Township facility it should be removed from the right-of-way.

Rockledge Park Program Elements

 

? Wetlands mapping

 

? Playground equipment

 

? Soccer practice field

 

? Small parking lot

 

? Picnic tables

 

? Basketball hoop

 

Town Hall Fields

 

The existing baseball field is in good condition and already has an irrigation system. The

basketball courts on site are in fair condition and need resurfacing and new backstops.

Installing a playground area will help satisfy a demand for playground equipment in the

central park of the Township. Due to the close proximity of facilities within the park it is

not recommended to install synthetic turf or lights on this field.

Town Hall Fields Program Elements

 

? Baseball field

 

? Playground equipment

 

? Picnic tables

 

Washington Park

 

Reconfiguring Washington Park provides the best opportunities to increase the number

of athletic fields in the Township. The Department of Public Works currently utilizes

approximately one third of the site as a dump site for spoils from construction work in the

Township, either by contractors or Township employees. This has a negative effect on

the natural and human environment in the park. The debris piles are beginning to

encroach within the wetland buffer and this area is highly visible when entering from

Jefferson Street leaving a negative impression with park users.

Washington Park should no longer be used as a dump site. Construction spoils should

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

113

 

be disposed of at an appropriate facility. Prior to cleaning up the site a Phase I

environmental analysis should be completed if it hasn’t been done previously. The site

should be cleaned to residential standards to allow for use as a public park.

Evaluating the site only spatially and from site visits (topographic information was not

available) it was found that by reconfiguring the entrance road from Jefferson Street a

baseball field and a soccer field as well as supporting parking, playground area and

walkways could be developed on site. The playground would meet the need for

playground equipment as part of a mini-park, in this part of town as well as a supporting

use for the siblings or children of athletes utilizing the fields. The new fields should be

developed with synthetic turf and sports lights.

This development would require NJDEP permits and would be predicated on completing

a buffer averaging plan where the proposed shift of the buffer is equal in ecological

value. If NJDEP will not accept the proposed transition area adjustment then the

baseball field can be reduced in size to a softball field.

Washington Park Program Elements

 

? Soccer field with synthetic turf

 

? Baseball field with synthetic turf

 

? Sports lights

 

? New and reconfigured parking lots

 

? Playground equipment

 

? Walkways

 

? Picnic tables

 

Woodland Lake

 

The majority of the area at Woodland Lake is the lake itself. The entrance off of

Alexander Avenue goes to a small gravel parking area with a couple benches and a boat

launch area. There are some trails through the vegetation. The lake edge at this point

has been reinforced with slabs of concrete creating a wall on either side of the boat

launch area.

Immediate improvements to this park should include reconstruction of the boat launch

and the addition of benches standard with the Township’s design standards and further

trail development. Long term improvements would include reconstruction of the lake

edge adjacent to the boat launch and lake edge habitat enhancement.

The Township’s Open Space and Recreation Plan recommended acquisition of Block

2701 Lots 2, 3 & 4. These parcels are recommended for acquisition as stated in the

OSRP as a buffer between developments between Rt. 23 and for trail development.

There currently is no access to the eastern side of the lake via land as the property lines

extend into the lake area.

Woodland Lake Program Elements

 

? Boat Launch reconstruction

 

? Lake edge wall reconstruction

 

? Lake edge habitat enhancement

 

Chapter 7 - Acquisition, Capital Improvement and

Maintenance Recommendations

PENNONI ASSOCIATES INC.

Consulting Engineers

 

114

 

? 0.2 miles of trail development

 

Other Land Acquisitions and Township Owned Lands

 

Pequannock Township’s Open Space and Recreation Master Plan identified other

parcels currently owned by the Township as undeveloped lands within Town with the

potential for use as recreation opportunities. The following section described these

parcels and their possible use for recreation opportunities.

Block 3708 Lot 1,8

These lands are located in the southern section of Town on Rt. 23 and near Pequannock

Avenue. They are within the floodway of the Pompton River and have wetlands located

on the lands. Access to the site is only from the south from Wayne. They are not

developable in accordance with current regulations and as such are not available for

recreation use. Acquisition is also not recommended at this time as state regulations

prohibit development of these parcels at this time thus, the ecological value of the land

will remain for the time being.

Block 2402 Lot 11

This parcel lies just west of West Parkway and in between the hospital and agriculture

lands. According to NJDEP GIS data the site is entirely wetlands and is in the middle of

a larger wetland area. State wetlands regulations would prohibit the development of this

parcel as active recreation. The Township already has varied opportunities for trail

development on other wetland parcels. Acquisition of this parcel is not recommended at

this time.

Block 4401 Lot 14

This parcel is the Pia Costa Tract. The owner intends to develop the site as a wetlands

mitigation bank. This would be a benefit for the Township to continue the sites ability to

help control flood waters and act as habitat for flora and fauna. The Township should

actively participate in the process to maintain the possibility for trail development

connecting Hidden Cove to the possible future developed trail on the railroad right-ofway.

No acquisition of this parcel is recommended.

Two other parcels, Block 302 Lot 2 and Block 202 Lot 23 were identified in the Open

Space and Recreation Plan as potential recreation sites. The first site has a commercial

building and parking on site. The second site has three commercial buildings and

parking on site. Neither of them is suitable for recreational use.

 

Design Guidelines

 

It is recommended that a coherent set of Design Guidelines be prepared as a first year

task. Over the upcoming years, these Guidelines can direct the work of various

landscape architects, engineers, foresters, architects, Township maintenance personnel

and volunteers in the appropriate design of the landscape and the facilities inserted into

it. Thus, the style and materials of construction will be readily understood and can be

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

115

 

applied to the Township’s parks over many years as the Master Plan recommendations

are implemented.

The Design Guidelines should include:

Structures

 

? Picnic shelters

 

? Façade treatment

 

? Rooflines and roofing materials

 

? Fenestration

 

? Bridges

 

? Culverts and other drainage structures

 

? Overlooks

Wayfinding System

 

? Size hierarchy for various purposes

 

? Color and material of signs

 

? Letter font and hierarchy

Landscape Elements

 

? Stone type and jointing for various uses (cobble, walls, drainage courses)

 

? Road surfaces

 

? Path materials, cross section, and edges

 

? Stairs for various conditions

 

? Handrails, guardrails, and fencing

 

? Bollards

 

? Bicycle racks

 

? Trash receptacles

 

? Picnic tables

 

? Fireplace and grill structures

 

? Benches

 

? Drinking fountains

 

? Light fixtures

 

? Various swale edges and water courses

Vegetation Management

 

? Native plantings for various purposes

 

? Establishment of new meadow edges and meadow installation

 

? Management for reestablishment and maintenance of vistas

 

Signage

 

Signage should be consistent throughout the Township (i.e. Woodland Lake). The

current signage is hard to read with black letters outlined in white on a dark wood

background. It is recommended that the signage be updated with letters easier to read

at a minimum. An opportunity exists to redesign the signage with a clear and consistent

hierarchy of sizes for various functions. A consistent language of form, color and

 

Chapter 7 - Acquisition, Capital Improvement and

Maintenance Recommendations

PENNONI ASSOCIATES INC.

Consulting Engineers

 

116

 

graphic design should also be developed for the park system. All entrances to the parks

should be clearly marked with such consistent signage. Informational signage could be

placed at historically significant locations describing the location such as overlooks in

Mountainside Park.

 

Actions

 

The following are actions to be completed based upon the previous recommendations.

The tasks are listed in priority order within each task category.

 

Immediate Actions (within one year)

 

1. Complete Greenview Park parking reconfiguration improvements.

2. Develop an action plan to pursue funding sources identified in the Open Space

and Recreation Plan to fund the recommended improvements.

3. Acquire funding to implement Hillview Fields improvements.

4. Remove DPW dump yard from Washington Park and remediate to residential

standards. Conduct a pre-application meeting with the NJ DEP to discuss the

proposed improvements.

5. Complete topographic and utility mapping for Washington Park improvements.

6. Develop and implement a comprehensive maintenance operations tasks and

schedule for each facility.

7. Begin negotiations for acquisition / agreement for use of Block 902 Lot 4 as a

soccer / lacrosse field with supporting parking.

8. Continue dialogue with the Board of Education on shared use for athletic fields

and existing field reconfiguration to expand field usage. Work with the sports

groups in town to leverage funding and manpower.

9. Further explore the programming and location for an indoor community

recreation facility.

10. Complete master plan for Pequannock Valley Park.

11. Develop a plan to coordinate all recreational opportunities and organizations

within the Township with possible shared scheduling of facilities.

12. Complete site development / park and recreation design guidelines.

13. Develop signage system and hierarchy.

14. Contact owners of farm assessed lands to encourage their participation in the

farmland preservation program.

 

Intermediate Actions (within three years)

 

1. Jointly implement Board of Education athletic field improvements with the BOE

and local recreation groups.

2. Develop a self-guided tour map along the adopted greenway identifying cultural,

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

117

 

social, recreational and environmental points of interest.

3. Complete wetlands mapping for Rockledge Park, Cherry Street Park, Hidden

Cove and Lyman Park.

4. Update Aquatic Park Master Plan

5. Develop “Friends of the Park” program.

6. Develop and adopt a Township Greenway Network.

7. Complete Hillview Fields Improvements.

8. Complete Washington Park improvements.

9. Complete Rockledge Park improvements

10. Implement signage improvements.

 

Intermediate Actions (within five years)

 

1. Complete soccer / lacrosse field improvements at Aquatic Park.

2. Riverside Park expansion feasibility study.

3. Complete Aquatic Park Master Plan recommendations.

4. Complete Hidden Cove improvements.

5. Complete Cherry Street Park improvements.

6. Implement Aquatic Park Master Plan.

7. Acquisition of parcels adjacent to Lyman Park (Block 4112 Lots 1&16).

8. Complete fundraising for Community Recreation Center.

 

Long Term Actions (within 10 years)

 

1. Implement Community Recreation Center.

2. Complete Woodland Lake improvements.

3. Complete remainder of Greenview Park improvements.

4. Update Park and Recreation Master Plan including the completion of a

statistically accurate user survey.

 

Ongoing Actions

 

1. Continued park maintenance.

2. Continue comprehensive maintenance operations tasks and schedule for each

facility.

3. Continued signage maintenance.

4. Continued streetscape improvements maintenance.

5. Add all new land acquisitions to the Township ROSI.

6. Actively participate in regional environmental issues (i.e. the Pia Costa Tract

 

Chapter 7 - Acquisition, Capital Improvement and

Maintenance Recommendations

PENNONI ASSOCIATES INC.

Consulting Engineers

 

118

 

wetland mitigation bank) and recreation issues (i.e. the Pequannock River Trail).

7. Monitor land acquisition opportunities for use as recreational facilities.

8. Monitor environmental regulations and possible weakening of regulations which

would increase land acquisition for environmental preservation up in priority.

9. Work with Morris County to implement regional trails within the Township

including along the railroad right-of-way.

10. Designate a Recreation Advisory Board member as liaison to each of the

environmental, historic, open space and street tree commissions.

11. Encourage stewardship of the parks and social ties through the “Friends of the

Park” program.

12. Seek continued input from the community regarding recreation programs and

facilities.

13. Implement the fund raising action plan.

 

The table titled Facility Strategy and Implementation on the following page identifies

the costs associated with the recommendations noted above. Itemized costs can be

found in Appendix A.

 

Pequannock Township Town-wide Park and Recreation Master Plan

 

Table 9 ~ Facility Strategy and Implementation Plan

 

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

119

 

Chapter 7 - Acquisition, Capital Improvement and

Maintenance Recommendations

PENNONI ASSOCIATES INC.

Consulting Engineers

 

120

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Appendices

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Appendix A – Estimates of Probable Costs

 

Description Quantity Unit Unit Cost Total Cost

 

Land Acquisition

 

Block 902, Lot 4 1 each $1,068,300.00 $1,068,300

 

Demolition

 

Tree removals 10 each $2,000.00 $20,000

subbase removal 2000 c.y. $15.00 $30,000

 

New Work

 

Earth work 10000 c.y. $26.00 $260,000

Asphalt paving 5600 s.y. $75.00 $420,000

Asphalt walk 4280 s.f. $6.00 $25,680

Player's benches 6 each $800.00 $4,800

Drainage 1 l.s. $30,000.00 $30,000

Subsurface drainage 1 l.s. $50,000.00 $50,000

Benches 6 each $1,180.00 $7,080

Play structure 1 each $45,000.00 $45,000

Safety surface 1 l.s. $58,000.00 $58,000

Trail 25600 s.f. $6.00 $153,600

Lawn (seed) 2000 s.y. $15.00 $30,000

Lawn (sod, athletic fields) 11500 s.y. $25.00 $287,500

Landscaping 1 l.s. $15,000.00 $15,000

Irrigation 1 l.s. $50,000.00 $50,000

Flag Poles 3 each $800.00 $2,400

Site lighting 20 each $2,500.00 $50,000

Bleachers (3 row, 42 seat) 2 each $5,000.00 $10,000

Drinking fountain 1 each $3,500.00 $3,500

 

Subtotal $1,552,560

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $310,512

 

DESIGN CONTINGENCY (15%) $232,884

 

CONSTRUCTION CONTINGENCY (7%) $108,679

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $232,884

 

TOTAL PROJECT PROBABLE COST $2,487,519

SAY $2,500,000

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Aquatic Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's experience

and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The engineer does

not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. A wetlands transition area plan must be approved by NJDEP for this layout. if averaging is not approved U-10 soccer field would need

to be reduced to a U-8 size field. This estimate of probable costs does not include any work regarding the existing wetland mitigation, or

sports lighting.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Playground equipment and safety surface does not include swings.

4. Unit costs include material, equipment and labor costs.

5. Land aquisition costs based upon current assessed value.

 

Y:\26150000\Docs\Estimate of Probable Costs\Aquatic Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Description Quantity Unit Unit Cost Total Cost

 

New Work

 

Trail 25600 s.f. $6.00 $153,600

Benches 3 each $1,180.00 $3,540

 

Subtotal $157,140

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $31,428

 

DESIGN CONTINGENCY (15%) $23,571

 

CONSTRUCTION CONTINGENCY (7%) $11,000

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $23,571

 

TOTAL PROJECT PROBABLE COST $296,710

SAY $300,000

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Cherry Street Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. NJDEP permit(s) are required to develop trails within wetland areas.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Unit costs include material, equipment and labor costs.

Y:\26150000\Docs\Estimate of Probable Costs\Cherry Street Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Foothills Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

Demolition

 

Tree removals 10 each $2,000.00 $20,000

Asphalt & subbase removal 1000 c.y. $45.00 $45,000

 

New Work

 

Community Center Building 35000 s.f. $220.00 $7,700,000

Asphalt paving 2000 s.y. $75.00 $150,000

Asphalt walk 5000 s.f. $6.00 $30,000

Earth work 5500 c.y. $26.00 $143,000

Retaining wall 340 l.f. $750.00 $255,000

4' ht chain link fence 340 l.f. $240.00 $81,600

Trail 3600 s.f. $5.00 $18,000

Player's benches 4 each $800.00 $3,200

Drainage 1 l.s. $65,000.00 $65,000

Subsurface drainage 1 l.s. $40,000.00 $40,000

Benches 10 each $1,180.00 $11,800

Lawn (seed) 3000 s.y. $15.00 $45,000

Lawn (sod, athletic fields) 3500 s.y. $25.00 $87,500

Irrigation 1 l.s. $75,000.00 $75,000

Flag Poles 3 each $800.00 $2,400

Site lighting 15 each $2,500.00 $37,500

Bleachers (3 row, 42 seats) 2 each $5,000.00 $10,000

Drinking fountain 1 each $3,500.00 $3,500

 

Subtotal $8,823,500

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $1,764,700

 

DESIGN CONTINGENCY (15%) $1,323,525

 

CONSTRUCTION CONTINGENCY (7%) $617,645

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $1,323,525

 

TOTAL PROJECT PROBABLE COST $13,902,895

SAY $14,000,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. This estimate of probable costs includes costs for a community center building based upon concept floor plans. The final

programming should be determined as part of the park master plan process.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Unit costs include material, equipment and labor costs.

Y:\26150000\Docs\Estimate of Probable Costs\Foothills Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Description Quantitiy Unit

Unit Cost

 

(Material, Equipment,

and Labor) Total Cost

 

Demolition

 

Tree removals (approximate) 30 each $2,000.00 $60,000

Asphalt and subbase removal 1200 s.y. $6.00 $10,000

Earthwork 2500 c.y. $5.00 $15,000

 

New Work

 

Asphalt roadway pavement (no curb) 2000 s.y. $40.00 $80,000

Asphalt topcourse 9500 s.y. $7.00 $66,500

Concrete Pavement 13500 s.f. $8.00 $110,000

Athletic turf (seed) 1.3 m.s.f. $300.00 $500

Topsoil (2") 800 c.y. $40.00 $32,000

Play spray (2,500 s.f. - 5 features) 1 l.s $100,000.00 $100,000

Picnic Shelter 1 l.s. $23,000.00 $23,000

Playground (Phase II) 1 l.s. $300,000.00 $300,000

Storm drainage allowance 1 l.s. $60,000.00 $60,000

$857,000

$171,400

$128,550

$59,990

$128,550

 

$1,345,490

 

SAY $1,400,000

 

* Excludes any work regarding existing utility pit, site lighting, restroom upgrades, and permit costs (if required).

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices, market

conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's experience and

qualifications and represents his best judgement as a design professional, familiar with the construction industry. The engineer does not

guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%

DESIGN CONTIGENCY (15%)

CONSTRUCTION CONTINGENCY (7%)

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Greenview Park

 

Programing Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

PROFESSIONAL FEES

 

TOTAL PROJECT COST

Subtotal

 

Y:\26150000\Docs\Estimate of Probable Costs\Greenview Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Hidden Cove

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

New Work

 

Trail 4000 s.f. $6.00 $24,000

Habitat enhancement 1 l.s. $100,000.00 $100,000

Asphalt pavement 300 s.y. $65.00 $19,500

 

Subtotal $143,500

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $28,700

 

DESIGN CONTINGENCY (15%) $21,525

 

CONSTRUCTION CONTINGENCY (7%) $10,045

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $21,525

 

TOTAL PROJECT PROBABLE COST $275,295

SAY $280,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. NJDEP permit(s) are required to develop trails within wetland areas.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Unit costs include material, equipment and labor costs.

Y:\26150000\Docs\Estimate of Probable Costs\Hidden Cove

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Hillview Fields

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

Demolition

 

Tree removals 30 each $2,000.00 $60,000

Asphalt and subbase removal 3484 c.y. $30.00 $104,520

Fence 365 l.f. $25.00 $9,125

 

New Work

 

Asphalt paving 8500 s.y. $75.00 $637,500

Asphalt walk 12500 s.f. $6.00 $75,000

Player's benches 6 each $800.00 $4,800

Infield clay (6" depth) 1900 c.y. $100.00 $190,000

Backstop 4 each $17,500.00 $70,000

10' high chain link fence 2000 l.f. $350.00 $700,000

Multi-purpose synthetic turf 1 l.s. $1,250,000.00 $1,250,000

Sports lighting 5 each $85,000.00 $425,000

Drainage 1 l.s. $55,000.00 $55,000

Benches 12 each $1,180.00 $14,160

Trash Receptacles 8 each $1,500.00 $12,000

Play structure 1 each $45,000.00 $45,000

Safety surface 1 l.s. $58,000.00 $58,000

Landscape 1 l.s. $20,000.00 $20,000

Shade Trees 30 each $280.00 $8,400

Flag Poles 3 each $800.00 $2,400

Site lighting 25 each $2,500.00 $62,500

Bleachers (3 row) 8 each $5,000.00 $40,000

Drinking fountain 3 each $3,500.00 $10,500

 

Subtotal $3,853,905

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $770,781

 

DESIGN CONTINGENCY (15%) $578,086

 

CONSTRUCTION CONTINGENCY (7%) $269,773

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES (15%) $578,086

 

TOTAL PROJECT PROBABLE COST $6,100,631

SAY $6,100,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices, market

conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's experience and

qualifications and represents his best judgment as a design professional, familiar with the construction industry. The engineer does not

guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. Layout will have to be finalized based upon a buffer averaging plan applicationapproval by NJDEP.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Playground equipment and safety surface does not include swings.

4. Unit costs include material, equipment and labor costs.

Y:\26150000\Docs\Estimate of Probable Costs\Hillview Fields

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Lyman Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

Demolition

 

Tree removals 10 each $2,000.00 $20,000

 

New Work

 

Earth work 11500 c.y. $26.00 $299,000

Asphalt walk 1600 s.f. $6.00 $9,600

Trails 9000 s.f. $5.00 $45,000

Player's benches 4 each $800.00 $3,200

Drainage 1 l.s. $30,000.00 $30,000

Subsurface drainage 1 l.s. $50,000.00 $50,000

Benches 6 each $1,180.00 $7,080

Lawn (sod, athletic fields) 11500 s.y. $25.00 $287,500

Bleachers (3 row, 42 seat) 2 each $5,000.00 $10,000

Drinking fountain 1 each $3,500.00 $3,500

 

Subtotal $764,880

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $152,976

 

DESIGN CONTINGENCY (15%) $114,732

 

CONSTRUCTION CONTINGENCY (7%) $53,542

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $114,732

 

TOTAL PROJECT PROBABLE COST $1,250,862

SAY $1,300,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. A wetlands delinieation will need to be completed as a part of the site development to verify limit of field development.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Unit costs include material, equipment and labor costs.

Y:\26150000\Docs\Estimate of Probable Costs\Lyman Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Lyon Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

Demolition

 

Play structure 1 each $10,000.00 $10,000

 

New Work

 

Earth work 300 c.y. $26.00 $7,800

Asphalt walk 500 s.f. $6.00 $3,000

Player's benches 4 each $800.00 $3,200

Benches 4 each $1,180.00 $4,720

Lawn (seed) 100 s.y. $25.00 $2,500

Play structure 1 each $45,000.00 $45,000

Safety surface 1 l.s. $58,000.00 $58,000

Flag Pole (25' ht) 1 each $800.00 $800

Drinking fountain 1 each $3,500.00 $3,500

 

Subtotal $138,520

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $27,704

 

DESIGN CONTINGENCY (15%) $20,778

 

CONSTRUCTION CONTINGENCY (7%) $9,696

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $20,778

 

TOTAL PROJECT PROBABLE COST $267,476

SAY $270,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. A wetlands transition area plan must be approved by NJDEP for this layout. if averaging is not approved U-10 soccer field would

need to be reduced to a U-8 size field. This estimate of probable costs does not include any work regarding the existing wetland

mitigation, or sports lighting.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Playground equipment and safety surface does not include swings

4. Unit costs include material, equipment and labor costs.

Y:\26150000\Docs\Estimate of Probable Costs\Lyon Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Mountainside Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

New Work

 

Trails 64000 s.f. $8.00 $512,000

Signage 10 each $1,500.00 $15,000

Trail Map Development 1 l.s. $15,000.00 $15,000

 

Subtotal $542,000

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $108,400

 

DESIGN CONTINGENCY (15%) $81,300

 

CONSTRUCTION CONTINGENCY (7%) $37,940

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $81,300

 

TOTAL PROJECT PROBABLE COST $900,940

SAY $900,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. This estimate of probable costs does not include any work regarding the existing parking lot.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. All work within Mountainside Park must be approved by the Highlands Council.

Y:\26150000\Docs\Estimate of Probable Costs\Mountainside Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Riverside Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

Demolition

 

Play structure 1 each $10,000.00 $10,000

 

New Work

 

Earth work 300 c.y. $26.00 $7,800

Asphalt walk 3600 s.f. $6.00 $21,600

Player's benches 4 each $800.00 $3,200

Benches 4 each $1,180.00 $4,720

Lawn (seed) 200 s.y. $25.00 $5,000

Play structure 1 each $45,000.00 $45,000

Safety surface 1 l.s. $58,000.00 $58,000

Flag Pole (25' ht) 1 each $800.00 $800

Drinking fountain 1 each $3,500.00 $3,500

 

Subtotal $159,620

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $31,924

 

DESIGN CONTINGENCY (15%) $23,943

 

CONSTRUCTION CONTINGENCY (7%) $11,173

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $23,943

 

TOTAL PROJECT PROBABLE COST $300,603

SAY $300,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. NJDEP permit(s) may be required to replace the playground structure.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Playground equipment and safety surface does not include swings.

4. Unit costs include material, equipment and labor costs.

Y:\26150000\Docs\Estimate of Probable Costs\Riverside Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Rockledge Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

Demolition

 

Tree removals 10 each $2,000.00 $20,000

 

New Work

 

Earth work 500 c.y. $26.00 $13,000

Asphalt paving 2400 s.y. $75.00 $180,000

Trail 20000 s.f. $8.00 $160,000

Player's benches 4 each $800.00 $3,200

Drainage 1 l.s. $15,000.00 $15,000

Subsurface drainage 1 l.s. $25,000.00 $25,000

Benches 5 each $1,180.00 $5,900

Play structure 1 each $45,000.00 $45,000

Safety surface 1 l.s. $58,000.00 $58,000

Lawn (sod, athletic fields) 11500 s.y. $25.00 $287,500

Landscaping 1 l.s. $25,000.00 $25,000

Irrigation 1 l.s. $50,000.00 $50,000

Site lighting 10 each $2,500.00 $25,000

Bleachers (3 row, 42 seat) 4 each $5,000.00 $20,000

Drinking fountain 1 each $3,500.00 $3,500

 

Subtotal $936,100

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $187,220

 

DESIGN CONTINGENCY (15%) $140,415

 

CONSTRUCTION CONTINGENCY (7%) $65,527

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $140,415

 

TOTAL PROJECT PROBABLE COST $1,519,677

SAY $1,600,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. A wetlands delineation approved by NJDEP is required to finalize development.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Playground equipment and safety surface does not include swings.

4. Unit costs include material, equipment and labor costs.

Y:\26150000\Docs\Estimate of Probable Costs\Rockledge Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Town Hall Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

Demolition

 

Tree removals 2 each $2,000.00 $4,000

 

New Work

 

Earth work 10000 c.y. $26.00 $260,000

Asphalt walk 3500 s.f. $6.00 $21,000

Player's benches 6 each $800.00 $4,800

Infield clay (6" depth) 800 c.y. $100.00 $80,000

Backstop 1 each $17,500.00 $17,500

4' ht chain link fence 650 l.f. $240.00 $156,000

10' ht chain link fence 500 l.f. $380.00 $190,000

Drainage 1 l.s. $65,000.00 $65,000

Subsurface drainage 1 l.s. $50,000.00 $50,000

Benches 8 each $1,180.00 $9,440

Play structure 2 each $45,000.00 $90,000

Safety surface 1 l.s. $70,000.00 $70,000

Lawn (seed) 2600 s.y. $15.00 $39,000

Lawn (sod, athletic fields) 3100 s.y. $25.00 $77,500

Shade Trees 15 each $280.00 $4,200

Landscaping 1 l.s. $25,000.00 $25,000

Irrigation 1 l.s. $100,000.00 $100,000

Flag Pole (25' ht) 1 each $800.00 $800

Sports lighting 1 l.s. $80,000.00 $80,000

Bleachers (3 row, 42 seat) 2 each $5,000.00 $10,000

Drinking fountain 2 each $3,500.00 $7,000

 

Subtotal $1,361,240

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $272,248

 

DESIGN CONTINGENCY (15%) $204,186

 

CONSTRUCTION CONTINGENCY (7%) $95,287

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $204,186

 

TOTAL PROJECT PROBABLE COST $2,187,147

$2,200,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's

experience and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The

engineer does not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

2. Playground equipment and safety surface does not include swings.

3. Unit costs include material, equipment and labor costs.

 

Y:\26150000\Docs\Estimate of Probable Costs\Town Hall Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Washington Park

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007

 

Pennoni Job No. 2615.0000

 

Description Quantity Unit Unit Cost Total Cost

 

Demolition

 

Tree removals 30 each $2,000.00 $60,000

Asphalt and subbase removal 3500 c.y. $30.00 $105,000

Fence (DPW Yard) 370 l.f. $25.00 $9,250

 

New Work

 

Earth work 10000 c.y. $26.00 $260,000

Asphalt paving 7700 s.y. $75.00 $577,500

Asphalt walk 18500 s.f. $6.00 $111,000

Player's benches 6 each $800.00 $4,800

Infield clay (6" depth) 470 c.y. $100.00 $47,000

Backstop 1 each $17,500.00 $17,500

4' ht chain link fence 1200 l.f. $240.00 $288,000

Drainage 1 l.s. $65,000.00 $65,000

Subsurface drainage 1 l.s. $50,000.00 $50,000

Benches 12 each $1,180.00 $14,160

Play structure 1 each $45,000.00 $45,000

Safety surface 1 l.s. $58,000.00 $58,000

Lawn (seed) 4500 s.y. $15.00 $67,500

Lawn (sod, athletic fields) 11500 s.y. $25.00 $287,500

Shade Trees 40 each $280.00 $11,200

Landscaping 1 l.s. $25,000.00 $25,000

Irrigation 1 l.s. $100,000.00 $100,000

Flag Pole (25' ht) 1 each $800.00 $800

Site lighting 35 each $2,500.00 $87,500

Bleachers (3 row, 42 seat) 4 each $5,000.00 $20,000

Drinking fountain 2 each $3,500.00 $7,000

 

Subtotal $2,318,710

 

GENERAL CONDITIONS, OVERHEAD, AND PROFIT (20%) $463,742

 

DESIGN CONTINGENCY (15%) $347,807

 

CONSTRUCTION CONTINGENCY (7%) $162,310

 

PERMIT COSTS (ALLOWANCE) $50,000

 

PROFESSIONAL DESIGN FEES $347,807

 

TOTAL PROJECT PROBABLE COST $3,690,375

SAY $3,700,000

 

Since the engineer has no control over cost of labor, materials, equipment, or over the contractor's methods of determining prices,

market conditions, or over competitive bidding; this estimate of costs for the Project is made upon the basis of the engineer's experience

and qualifications and represents his best judgment as a design professional, familiar with the construction industry. The engineer does

not guarantee that proposals, bids, or the project construction cost will not vary from this cost estimate.

Notes:

1. A wetlands buffer averaging plan must be approved by NJDEP for this layout.

2. Permit Costs include storm drainage design, preparation of NJDEP and SESC permit applications and permit fees.

3. Playground equipment and safety surface does not include swings.

4. Unit costs include material, equipment and labor costs.

 

Y:\26150000\Docs\Estimate of Probable Costs\Washington Park

 

Pequannock Township Town-wide Park and Recreation Master Plan

PENNONI ASSOCIATES INC.

Consulting Engineers, Landscape Architects and Planners

 

Pequannock Township Town-Wide Park and Recreation Master Plan

 

Pequannock Township, Morris County, New Jersey

 

Woodland Lake

 

Programming Estimate of Probable Costs

 

Professional Planning and Engineering Division of Pennoni Associates, Inc.

March 2007